Installation / Assembly
T-Rack
®
3.0 Series
– Assembly Instructions 1.1(2019-03) E inge
Page 36 of 84
© inge GmbH
Floor Characteristics
Ensure that the floor characteristics meet the following minimum requirements
Level, smooth surface with the necessary strength
Recommendation: gullies and drainage channels ensure adequate water drainage, e.g. when
emptying the T-Rack
®
s.
Checking the Floor Load
Ensure that the maximum permissible floor load of the planned system footprint is not exceeded.
The maximum permissible floor load must be at least 2,500 kg/m
2
.
CAUTION
DANGER OF INJURY!
Danger of injury and system damage due to exceeding the
maximum permissible floor load.
Do not exceed the maximum permissible for load!
5.3.2
Protecting the Work Area
Structure of the Work Area
The work area consists of the following areas:
The single parts of the sub-unit that are in storage, have been unpacked, are being tested and/or
are being processed,
The pre-assembled assembly groups,
The sub-unit currently being processed,
The final location of the sub-unit and the T-Rack
®
and additionally on all routes:
All required access routes to the areas specified above,
All required walking and driving distance between the areas specified above,
All escape routes from one of the area or routes specified above