3.29 BOILER REGISTRATION.
This Commissioning Checklist is to be com-
pleted in full by the competent person who
commissioned the boiler as a means of demon-
strating compliance with the appropriate
Building Regulations.
Failure to install and commission according to
the manufacturer’s instructions and complete
this Commissioning Checklist may invalidate
the warranty.
Customer name:
Telephone number:
Address:
Boiler make and model:
Boiler serial number:
Commissioned by (PRINT NAME):
Plumbing license number:
Company name:
Telephone number:
Company address:
Commissioning date:
Commissioning date:
Certificate of compliance number:
CONTROLS
(tick the appropriate boxes)
Time and temperature control to heating
Room thermostat and programmer/timer
Programmable room thermostat
Weather compensation
Optimum start control
Time and temperature control to hot water
Cylinder thermostat and programmer/timer
Combination boiler
Heating zone valves
Fitted
Not required
Hot water zone valves
Fitted
Not required
Thermostatic radiator
Fitted
Not required
Automatic bypass to system
Fitted
Not required
Boiler interlock
Provided
ALL SYSTEMS
The system has been adequately flushed and cleaned?
Yes
What system cleaner was used?
What inhibitor was used?
Quantity
Litres
Has a system filter been installed?
Yes
No
HEATING MODE
measure and record:
Burner inlet gas working pressure (at maximum rate)
Kpa
OR
gas inlet pressure
Kpa
Central heating flow temperature
°C
Central heating return temperature
°C
COMBINATION BOILER - DOMESTIC HOT WATER MODE
measure and record:
Burner inlet gas working pressure (at maximum rate)
Kpa
OR
gas inlet pressure at maximum rate
Kpa
Cold water inlet temperature
°C
Hot water has been checked at all outlets
Yes
Temperature
°C
Has a DHW tempering valve been fitted to sanitary fittings?
Yes
Temperature
°C
Water flow rate
I/min
CONDENSING BOILERS ONLY
The condensate drain has been installed in accordance local laws in force?
Yes
ALL INSTALLATIONS
Record the following:
At max. Rate:
Co
Ppm Co
²
%
Ratio CO/CO
Ratio
At min. Rate: (where possible)
Co
Ppm Co
²
%
Ratio CO/CO
Ratio
The heating and hot water system complies with the appropriate Building Regulations
Yes
The boiler and associated products have been installed and commissioned in accordance with the manufacturer’s instructions
Yes
The operation of the boiler and system controls have been demonstrated to and understood by the customer
Yes
The manufacturer’s literature, including Commissioning Checklist and Service Record, has been explained and left with the customer
Yes
Commissioning Engineer’s Signature
Customer’s Signature
(To confirm satisfactory demonstration and receipt of manufacturer’s literature)