To ensure adequate cooling, plan to install the chassis with the port side facing
the aisle where exhaust air is released (usually called the service aisle). This
prevents the fans from pulling in heated exhaust air.
4.
Plan for managing the cables before you install the chassis. A fully populated
SAN384B-2 will have a large number of cables that must be carefully routed to
minimize problems with installation and replacement of components, and in
order to maintain the minimum bend radius required for optical cables. Due to
port density and the potentially large number of cables, if cables are not routed
to the sides, then removal and replacement of blades and other components
may be difficult to accomplish. Refer to “Managing cables” on page 44 for more
specific information. You can manage the cables in a variety of ways, such as:
v
Routing the cables through the vertical cable management finger assemblies
installed on either side of the chassis
v
Routing the cables out to either side of the chassis
v
Routing the cables through the cable channels on the sides of the cabinet
v
Using patch panels
5.
Ensure that the following are available for configuration:
v
Workstation with an installed terminal emulator, such as HyperTerminal
v
Serial cable (provided)
v
Three Ethernet cables (including one spare)
v
Access to an FTP server for backing up the switch configuration or collecting
supportsave output data (optional)
v
Brocade USB drive for collecting supportsave output data (optional)
v
SFPs and compatible cables
6.
Ensure that the air intake vents have a minimum of 2 inches of airspace.
7.
Ensure that the air temperature on the air intake side is less than 40°C (104°F )
during operation.
Installing a SAN384B-2 in a 2109 C36 cabinet
This section describes how to install the SAN384B-2 in the Model C36 cabinet.
These procedures use parts that are included in the hardware accessory kit and the
port-side exhaust kit, which also functions as a lower supporting shelf. No
rack-mount rail kit is required for this installation.
To safely complete the installation, a minimum of two people are required.
Time required
Allow approximately 3 hours to complete this entire procedure. This total includes
unpacking, assembling, disassembling, and repacking the lift tool. The time
estimate is for the physical installation of the SAN384B-2 only. It does not include
installing Ethernet cables, transceivers, attaching and routing the fiber optic cables,
or completing the initial configuration.
The SAN384B-2 and the lift tool should be delivered to a location near to the final
installation, with clear aisles for maneuvering the lift tool loaded with the chassis.
Since the lift tool can be used to move the chassis the short distance from the
delivery location to the installation, it is recommended that you assemble the lift
tool before starting the installation steps.
14
SAN384B-2 Installation, Service, and User Guide
Содержание SAN384B-2
Страница 2: ......
Страница 8: ...vi SAN384B 2 Installation Service and User Guide ...
Страница 12: ...x SAN384B 2 Installation Service and User Guide ...
Страница 14: ...xii SAN384B 2 Installation Service and User Guide ...
Страница 16: ...xiv SAN384B 2 Installation Service and User Guide ...
Страница 28: ...xxvi SAN384B 2 Installation Service and User Guide ...
Страница 32: ...xxx SAN384B 2 Installation Service and User Guide ...
Страница 82: ...50 SAN384B 2 Installation Service and User Guide ...
Страница 146: ...114 SAN384B 2 Installation Service and User Guide ...
Страница 172: ...140 SAN384B 2 Installation Service and User Guide ...
Страница 182: ...Taiwan Class A Electronic Emission Statement 150 SAN384B 2 Installation Service and User Guide ...
Страница 187: ...WWN bezel 65 card status 65 WWN bezel installing 88 removing 88 WWN card failure 65 removing 88 Index 155 ...
Страница 188: ...156 SAN384B 2 Installation Service and User Guide ...
Страница 189: ......
Страница 190: ... Part Number 98Y2654 Printed in USA GA32 0894 03 1P P N 98Y2654 ...