Installing the Frames
1 Removing the packing material
1. Remove all of the tape and packing
material from the outside of each frame
(save shipping materials and container).
2. Inventory the components.
3. Remove all of the tape and packing
material from the inside of each frame.
2 Preparing the frames
1. Position each frame according to the
customer floor plan.
There can be a maximum of three
frames to a 7060 String.
The first frame contains the CPC and
the Support Element.
The second frame can be a:
a. I/O 01 a channel and DASD cage.
The third cage can only be a:
a. I/O 02 a DASD cage only.
Top
View
Processor
Cabinet
(Cabinet 2)
Top
View
I/O - DASD
Cabinet
Cabinet 1)
Top
View
DASD only
Cabinet
(Cabinet 3)
Rear
Rear
89 mm
(3.5 in)
521 mm
(20.5 in)
89 mm
(3.5 in)
521 mm
(20.5 in)
762 mm
(30 in)
3264 mm
(128.5 in)
521 mm
(20.5 in)
762 mm
(30 in)
EPO
Switch
EPO
Switch
EPO
Switch
Chapter 1. Beginning the Installation
1-7
Содержание Multiprise 3000 S/390
Страница 1: ...S 390 Multiprise 3000 Enterprise Server R IBM Installation Manual SY24 6154 03...
Страница 2: ......
Страница 3: ...S 390 IBM Installation Manual SY24 6154 03...
Страница 8: ...vi Installing the System...
Страница 14: ...xii Installing the System...
Страница 34: ...1 20 Installing the System...
Страница 40: ...2 6 Installing the System...
Страница 78: ...5 20 Installing the System...
Страница 156: ...6 78 Installing the System...
Страница 160: ...7 4 Installing the System...
Страница 172: ...B 4 Installing the System...
Страница 173: ......
Страница 174: ...IBM Printed in the United States of America on recycled paper containing 10 recovered post consumer fiber SY24 6154 3...
Страница 175: ...Spine information IBM S 390 Installation Manual...