22

The input gas must fit for the system gas supply requirements, if use high press gas cylinder supply gas, must choose

good quality gas regulator to ensure the gas pressure stable

When adopt O

2

as the plasma gas, there is risk for fire, so exhaust ventilation system must be installed, after

installation, must check if there is any leak

Gas type

For different cutting material adopts different gas

Material

Plasma gas

Shield gas

C.S

Air

Air

O

2

Air

S.S or Al.

Air

Air

N

2

N

2

N

2

Air

Air/Air cutting, gas hose connect

When connect Air/Air, only need connect

16 and

17, connect compressed air to plasma and shield gas regulator filter,

no need N

2

or O

2

N

2

/N

2

cutting, gas hose connect

When connect Air/Air, only need connect

16 and

17, connect compressed air to plasma and shield gas regulator filter,

no need Air or O

2

O

2

/Air cutting, gas hose connect

When adopt O

2

as the plasma gas, Air as the shield gas, gas hose connect as:

Plasma gas hose connection:

18 shield gas hose, take off from the plasma gas inlet terminal from back of the machine,

then connect the filtered and flow adjusted O

2

(the O

2

gas hose should be out diameter 10mm soft hose),customer need

prepare good quality O

2

gas regulator instead of the gas filter at back of the machine to ensure safety.

Shield gas hose connection:

16 shield gas hose, connect compressed air to the shield gas regulator inlet connector.

No need N

2

11. Filling coolant liquid

Improper coolant will cause damage for the machine

Please refer to the coolant requirements

Coolant capacity of the cooling system is 20 liters, the specific capacity depends on the length of the integrated cable.
Firstly, pour coolant into power until the bucket is filled. Power indicator of cutting power panel and liquid level

indicator should be on; water pump in cutting power supply starts to work, then the liquid flow indicator is lit. (If the cable

length is longer (more than 50 meters), the cooling fluid level will decrease and panel liquid level indicator will be

extinguished after the pump works for a while, then the water pump stops working. In this case, please turn off the power,

fill cooling liquid into the bucket again, and turn on power supply until the coolant flow is normal, panel liquid flow indicator

is lit.

Finally, turn off the power; fill the cooling fluid into the bucket and cover bucket.

12. Setting of gas supply

Start the gas supply equipment, open the gas supply switch. Turn on the power, the pressure indicator of cutting power

panel should be lighted. If the pressure is less than 0.2Mpa, the air pressure indicator will not be lighted, need to check the

gas supply.

Place the gas control switch to "check gas" position, adjust the plasma gas and protecting gas pressure to make the

output pressure or flow satisfy cutting requirements (please see the cutting table for regulated value), after adjustment,

Содержание SLG-200HF

Страница 1: ...SLG 200 300 400HF PLASMA CUTTING MACHINE MANUAL INSTRUCTION PLEASE READ IT CAREFULLY BEFORE OPERATION...

Страница 2: ...uitable 4 The cutter has external static characteristic with rated duty cycle 100 which means the machine can work continuously at the rated cutting current The machine has the function of thermal pro...

Страница 3: ...rc Use an arc welding mask to protect your eyes and skin from sparks and the rays of the arc pay special attention to the filter glass which must be conformable to the national standard Use clothing m...

Страница 4: ...dd fuel after engine is cooling down otherwise the evaporation of hot fuel would result in dangers Do not splash fuel out of the fuel tank and do not start the engine until complete evaporation of the...

Страница 5: ...e It is better to push the welding machine moving in use of its rollers unless special situations Be sure that the appurtenances are all removed off when lifting When lifting make sure that there is n...

Страница 6: ...Arc initiator panel 11 3 Secondary menu 12 Installation 13 1 Acceptance inspection 13 2 Product defect 13 3 Installation requirement 13 4 Noise 13 5 Ground connection and shield installation 13 6 Ins...

Страница 7: ...shooting 32 4 Control panel indicator instruction 35 5 Initial inspection 36 6 Air filter cartridge replace 36 7 Cutting machine cooling system maintenance 37 8 Maintenance 38 Appendix 39 1 Cutting m...

Страница 8: ...e 2 Arc initiator Plasma arc initiator QFK E1 is used for the HF pulse start then cause guide arc when the guide arc reach the workpiece it will cause main arc Another function for the arc initiator i...

Страница 9: ...ng system with import big flow pump and big power heat sink construction so that torch work stable and constant 6 Gas pre send gas delay shut current up slope time can be set 7 Machine have overheat g...

Страница 10: ...he machine in a clear place without any of dust corrosive gas and flammables and explosives Do not use it in open air and rain 2 Required air relative humidity should 90 at 20 40 50 at 40 3 Environmen...

Страница 11: ...ure MPa 0 5 0 7 Quality cutting thickness C S mm 25 32 40 Insulation grade F Cooling mode Air cooling Protection grade IP21S Note The cutting thickness data got from our standard parts testing even it...

Страница 12: ...5 3 2 SLG 300HF dimension and weight 3 3 SLG 400HF dimension and weight...

Страница 13: ...6 3 Characteristics 3 4 SLG 200HF 3 5 SLG 300HF 3 6 SLG 400HF 2 Arc initiator QFK E1 3 7 QFK E1 dimension and weight...

Страница 14: ...ediately with lot of clean water then go to the hospital to ask for help Notice Do not use the anti freezing solution as the coolant it hurt the torch To protect the bump and torch cooling system plea...

Страница 15: ...ord with the below table standard Both the lowest and highest index If use water without according with below lowest purity index there will be too much precipitate on electrode which affect the water...

Страница 16: ...this know 5S without loss can start the manual pump function Manual pump function force to start the cooling system the display knob automatically change to coolant flow display 3 Coolant temperature...

Страница 17: ...3s then off 0 3s machine lack phase or over voltage or lack voltage machine can t work 13 Current adjusting knot it adjust the cutting current under the secondary menu to adjust the secondary menu pa...

Страница 18: ...s the work piece cable Work piece cable is also called the ground cable 40 Water coolant liquid inlet connector to connect the coolant liquid return pipe 41 Water coolant liquid outlet connector to co...

Страница 19: ...00 S 0 15 After arc strike success the exact current will up to the set value P04 Set cutting time 1 999 Min 999 Set the torch consumables cutting time After set the related P06 value will upgrade ac...

Страница 20: ...ne ground connect It need a cable from cutting machine positive to cutting table ground connect It need plate install on the cutting table and well connect with workpiece RF1 and EMI ground connect an...

Страница 21: ...to connect the rail terminal If need add voltage depressor for use in the CNC system it should install nearby the voltage sample place Inside the plasma machine is suitable the signal should within t...

Страница 22: ...15 5 2 Installation Drawing System components A Plasma power sourceSLG 200HF 300HF 400HF...

Страница 23: ...ive cable 12 Coolant return pipe 13 Coolant supply pipe 14 Work cable earth cable 15 Torch cable 16 Shield gas input hose 17 Shield gas input hose N2 Air 18 Plasma gas input hose O2 7 Installation of...

Страница 24: ...urce This breaker should be a When OFF it isolate the electric and cut all the conductive and plasma machine b OFF and ON use O and I to indicate c Prepared a manipulate handle can lock the OFF positi...

Страница 25: ...10 Cable and hose installation 5 2 1 18 1 Power supply cable Danger Shock may cause people die When install the cable the switch must be OFF a Take off the back cover install the power cable to the po...

Страница 26: ...rches positioning finish 2 Suitable for under water cutting torch have air first to blow the water then positioning and strike arc to ensure the under water cutting smooth 3 Can control the gas pre fl...

Страница 27: ...potentiometer pin 9 10 on can directly control the loading capacity as 0 5A 125VAC or 0 2A 110VDC or 1 0A 24VDC pin 9 10 off when there is no arc strike success signal 9 Arc strike success signal 10 P...

Страница 28: ...d well to reliably connect work cable and cutting power source the other side of the cable connect with the cutting table reliably When work cable 30m it will affect the cutting quality so the square...

Страница 29: ...ssed air to the shield gas regulator inlet connector No need N2 11 Filling coolant liquid Improper coolant will cause damage for the machine Please refer to the coolant requirements Coolant capacity o...

Страница 30: ...lag and smooth 1 Notice for use cutting table and torch Check the vertical of the torch Clean the rail and transmit device on the cutting table to get smooth torch move If not stable will cause cuttin...

Страница 31: ...s slag a Reduce the cutting speed b Decrease the arc voltage shorten the distance between torch to workpiece c Increase the O2 in shield gas the manual gas console not work with the mix shield gas but...

Страница 32: ...or other parts which not suggest 14 Inspection before operate Before start the machine make sure cutting surrounding environment and protective suit meet requirements according to safety of manual an...

Страница 33: ...nside cap nozzle Vortex Electrode HY02711 HY02701 HY02601 HY02501 HY02423 HY02301 HY02211 Plasma gas Protective gas Work piece thickness Distance Torch to work piece Arc voltage Cutting speed Piercing...

Страница 34: ...p Inside cap nozzle Vortex Electrode HY02711 HY02701 HY02601 HY02501 HY02419 HY02301 HY02211 Plasma gas Protective gas Work piece thickness Distance Torch to work piece Arc voltage Cutting speed Pierc...

Страница 35: ...ide cap Inside cap nozzle Vortex Electrode HY02711 HY02701 HY02601 HY02501 HY02417 HY02301 HY02211 Plasma gas Protective gas Work piece thickness Distance Torch to work piece Arc voltage Cutting speed...

Страница 36: ...Inside cap nozzle Vortex Electrode HY02711 HY02701 HY02601 HY02501 HY02423 HY02301 HY02211 Plasma gas Protective gas Work piece thickness Distance Torch to work piece Arc voltage Cutting speed Pierci...

Страница 37: ...to work piece Arc voltage Cutting speed Piercing height Piercing time L min MPa L min MPa mm mm V mm min mm S 34 0 4 70 0 6 6 2 140 3000 4 0 4 10 2 5 145 2800 5 0 6 12 3 152 2300 6 0 8 15 3 5 157 1600...

Страница 38: ...No default phase No radiator overheat protection signal No liquid overheat protection signal No plasma arc signal 2 Blow 24s Air or N2 to torch continues for 24s Turn on cooling system power Check ai...

Страница 39: ...2 Pause overtime Pause signal expire time over 60s 1 Check X6 cable at back of power source whether damaged 2 CNC still maintain the signal may wait for another torch initial location signal 3 If the...

Страница 40: ...radiator and fan 3 If radiator temperature not high and alarm main machines temperature high shall check the temperature relay whether damage 071 Coolant temperature high Coolant temperature over 70...

Страница 41: ...mer CNC give start signal to plasma power source but machine no action 1 gas signal of external power source problem 2 PCB PL18 of power source is damaged 1 Check the start indicator on the power sour...

Страница 42: ...source refer to nameplate 4 Control panel indicator instruction On PCB PL18 and PL02 have the LED indicator problem can be solved according to the status of the indicator 1 PCB PL18 LED code Indicator...

Страница 43: ...ere is error appear LED34 on the alarm signal output from X5 at back of the machine 2 PL02 LED code Indicator function Instruction D1 Cooling system power supply Power supply D1 on D2 Main circuit coo...

Страница 44: ...eck coolant filter Observe from outside if too much impurities inside filter during coolant system working but no cutting status open filer drain valve discharge impurities note discharge by soft tube...

Страница 45: ...d please replace 2 Cooling system Replace the coolant regularly 6 month or 300 hours Check the coolant flow regularly add if need Check the coolant filter under the cutting machine front panel clean a...

Страница 46: ...ier V101 V201 SLG 200HF 400HF MDS150 16 13 Temperature relay KT101 KT201 KSD305A Shut 75 14 Flow switch BP1 ES12010 2 2A1 220V 15 Flow sensor BP2 SEN HZ21WD B 16 Valve YV1 VX2120 10 17 Pump Pump head...

Страница 47: ...40 3 Circuit diagram 7 1 SLG 200HF...

Страница 48: ...41 7 2 SLG 300HF...

Страница 49: ...42 7 3 SLG 400HF...

Страница 50: ...43 7 4 QFK E1...

Страница 51: ...gister qty 2 2 Deputy station react frame a react correct frame Function code and instruction Deputy station address Functi on code Register address Register quantity Function code and instruction Dep...

Страница 52: ...0s Data is times of 0 01s 12 Manual pump function 43002 1 0 1work 13 Cutting time set 43003 1 999min 14 Penetration times set 43004 1 999 15 Monitoring control switch 43005 1 0 1 work 16 Monitoring al...

Страница 53: ...s in the user s manual forgive not to inform separately Chengdu Huayuan Electric equipment Co Ltd Address Wuhou National Science Park Chengdu China Postcode 610045 Telephone 0086 28 85744098 Fax 0086...

Отзывы: