UPS5000-S-880 kVA
User Manual (CMI)
3 Installation
Issue 02 (2020-01-10)
Copyright © Huawei Technologies Co., Ltd.
61
Figure 3-15
Hole dimensions (unit: mm)
Step 2
Drill cabinet mounting holes in channel steel by using a hammer drill.
----End
Combining Power Cabinets and Bypass Cabinets
Step 1
The power cabinets and bypass cabinets are combined in the same way for ground installation
and channel steel installation.
----End
Securing the UPS
Step 1
Use common M12x60 bolts to secure the cabinets into the mounting holes in the channel steel
and tighten the bolts.
Step 2
Install the front, rear, left, and right anchor baffle plates.
----End
3.2.2 Installing Batteries
Context
Before installing batteries, read through the battery safety precautions, obtain the delivered
battery installation guide, and install batteries as instructed.
Place the batteries in a correct way to prevent vibrations and shocks.
Install the batteries from the lower layer to the upper layer to prevent falling over due to
imbalance.