6.3.3.2 Installing Copper Bars and Cables
Context
Figure 6-63 Copper bar positions
(1) Battery input
(2) Mains input
(3) Battery PE
(4) UPS output
(5) Bypass input
NO TE
The number and colors of cables in the following figures are for reference only.
Procedure
Step 1 Remove the top covers from the bottom cabling cabinet and the battery copper
bars.
Figure 6-64 Removing the covers and battery copper bars
Step 2 Install epoxy boards (No. 1 to 8).
UPS5000-H-(1200 kVA-1600 kVA)
User Manual (100 kVA Power Modules)
6 Installation
Issue 05 (2021-10-13)
Copyright © Huawei Technologies Co., Ltd.
124