NO TE
● The input circuit breakers recommended are for reference only.
● If multiple loads are connected, use recommended specifications for branch circuit
breakers.
● The circuit breaker selection principle is to protect loads and cables, and the cascading
principle is to achieve specific protection.
6.1.4 Unpacking
Context
NO TICE
● Only trained personnel are allowed to move the UPS. Use a pallet truck to
transport the UPS case secured to a wooden support to the installation
position.
● To prevent the UPS from falling over, secure it to an electrical pallet truck using
ropes before moving it.
● Move the UPS with caution to avoid bumping or toppling, which may damage
the UPS. After placing the case in the installation position, unpack it with
caution to prevent scratches. Keep the UPS steady during unpacking.
● If the UPS installation environment is in poor condition and the UPS needs to
be stored for a long time after it is unpacked, take measures to prevent dust. It
is recommended that the UPS be wrapped with the original plastic coat.
Procedure
Step 1 Use a pallet truck to transport the UPS to the installation position.
Step 2 Remove the UPS outer packing.
Step 3 After confirming that the UPS is intact, remove the bolts that secure the UPS to
the pallet and remove the UPS from the pallet.
Figure 6-29 Unpacking (1600 kVA power cabinet 1)