Figure 6-9 Preparing a cable terminal outside the cabinet
NO TE
Choose an appropriate cabling route based on the actual situation. The figure is for
reference only.
Step 4 Connect the cable with a crimped terminal to the corresponding copper bar.
Step 5 Clear sundries inside the cabinet.
----End
6.3 Single UPS Installation (400–600 kVA)
CA UTION
When you install the UPS and connect cables, do not step on the front door baffle
plate and the door support at the bottom of the cabinet to prevent paint flake-off
and deformation. Otherwise, the front door will not be properly closed.
6.3.1 Installing the UPS
6.3.1.1 Installing the Cabinet
Installation on the Floor
NO TICE
Ensure that the installation floor is level.
Step 1 Install the cabinet.
1. Determine the mounting holes for the cabinet based on the marking-off
template. A indicates the mounting holes for channel steel. B indicates the
mounting holes for the floor. The unit is mm.
UPS5000-H-(400 kVA-800 kVA)
User Manual (100 kVA Power Module)
6 Installation
Issue 02 (2021-04-22)
Copyright © Huawei Technologies Co., Ltd.