3 Installation
Issue 07 (2019-12-13)
Copyright © Huawei Technologies Co., Ltd.
58
Figure 3-12
Castors off the floor
Step 2
Check whether the bottom of the cabinet is horizontal by using a level. If the cabinet is not
leveled, adjust the leveling feet.
----End
3.2.2 Installing Optional Components
3.2.2.1 Installing Antiseismic Kits
Context
Before removing the rear cover from the cabinet, ensure that battery modules have not been
installed to prevent electric shocks.
Procedure
Step 1
Determine the installation positions for the antiseismic kits based on the delivered
marking-off template, and mark mounting holes, as shown in