86
Figure 3-36
Removing the front covers of the power distribution subrack
Step 7
Remove the rear covers from power cabinet 1 and its adjacent bypass cabinet.
Step 8
(Optional) Remove the extension rod of the maintenance bypass switch from the bypass
cabinet.
To facilitate cabinet combination, remove the switch extension rod from the left bypass cabinet. The
operation of removing the switch extension rod from the right bypass cabinet is optional.
Put away the removed screws, washers, and switch extension rod which need to be reinstalled after
cables are connected.
When reinstalling the switch extension rod, keep the dowel level, as shown in
. Insert the
switch extension rod to the blue mark, put washers, and tighten the slotted screw to reinstall the