3 Installation
Issue 03 (2019-12-13)
Copyright © Huawei Technologies Co., Ltd.
58
----End
3.2.2 (Optional) Installing Antiseismic Kits
Step 1
Determine the positions for installing antiseismic kits based on the marking-off template.
Step 2
Drill holes for installing expansion bolts, and install expansion bolts.
Step 3
Move the UPS to the installation position over its castors.
Step 4
Remove the PDU cover.
Step 5
Secure two antiseismic kits to the front and rear of the chassis using eight M6 screws and four
M12 screws
Figure 3-22
Securing antiseismic kits to the cabinet
Step 6
Adjust the cabinet position so that the expansion bolt holes are aligned with the four holes at
the bottom of the cabinet.
Step 7
Check the cabinet levelness using a level. If the cabinet is not leveled, adjust the leveling feet.
Step 8
Secure the two antiseismic components to the floor using four M12x60 expansion bolts.
Step 9
Reinstall the PDU cover.
----End
3.2.3 (Optional) Installing a Battery Monitoring Unit
Connect the BMU by using a 04080298 transfer cable, which is delivered with the BMU.
When no ambient temperature and humidity sensor is installed, connect the BMU to the
COM1 port on the UPS.
shows the position of the BMU on the UPS.
When an ambient temperature and humidity sensor is installed, connect the BMU to the
RS485_OUT port on the sensor.