SmartLogger2000
User Manual
7 WebUI
Issue 04 (2018-04-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
153
Figure 7-49
Power meter 1
Figure 7-50
Power meter 2
Enabling of the Power Meter Feedback of Grid Connection Data
If a power meter is connected in the PV plant and needs to provide feedback of the grid
connection data through the AO port of the SmartLogger, set
Meter feedback output
to
Enable
and then set port parameters as required.