8 Power Grid Scheduling
Issue 12 (2019-01-15)
Copyright © Huawei Technologies Co., Ltd.
260
Figure 8-6
Remote scheduling
Disable
,
Strategy 1
, and
Strategy 2
are available for
Schedule strategy
.
Disable
: The SmartLogger controls the inverter to work at full load and will not receive scheduling
commands sent by the NMS.
Strategy 1
: Open-loop scheduling policy. That is, the SmartLogger evenly allocates the power value
from the scheduling and delivers the average values to each inverter, which then operates with the
specific power. The adjustment value delivered by the SmartLogger is constant.
Strategy 2
: The customized function is provided for a site.
Adjustment coefficient
: The power value will be sent to the inverter after being multiplied by the preset
coefficient.