8 Installation Verification
Issue 03 (2020-04-10)
Copyright © Huawei Technologies Co., Ltd.
67
8
Installation Verification
After installing the cabinet and all equipment, check the installation items, installation
environment, and cables.
Checking the Cabinet Installation
Table 8-1
Cabinet installation checklist
No. Check That
Result
1
The cabinet is placed in accordance with the design
drawing.
□ Yes □ No
2
The base is secured.
□ Yes □ No
3
All bolts, especially the bolts used for electrical
connections, are fully tightened. Flat washers and spring
washers are all installed in correct sequence.
□ Yes □ No
4
The cabinet is clean, free of dust and dirt.
□ Yes □ No
5
All labels are correct, clear, and complete.
□ Yes □ No
Checking the Environment
Table 8-2
Environment checklist
No. Check That
Result
1
There are no unnecessary adhesive tape or cable ties on
cables.
□ Yes □ No
2
There are no adhesive tapes, cable ties, paper scraps, or
packing materials around the cabinet.
□ Yes □ No