PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
7 Installing Cables
Issue 03 (2020-04-10)
Copyright © Huawei Technologies Co., Ltd.
63
Step 2
Connect the signal cable from the battery temperature sensor to the BTEMP terminal on the
UIM02C, as shown in the following figure.
Figure 7-21
Installing the signal cable for a battery temperature sensor
----End
7.9 Installing AC Input Power Cables
Prerequisites
AC input power cables need to be installed when a backup DG is available.
Ensure that the upstream AC input circuit breaker is OFF, and attach labels such as "No
operations allowed."
Switch off all circuit breakers before installing power cables.
Procedure
Step 1
Prepare a suitable length cable based on site requirements. Install a cord end terminal or an
OT terminal on each end of the cable.
Step 2
Install AC input power cables.