
PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
7 Installing Cables
Issue 03 (2020-04-10)
Copyright © Huawei Technologies Co., Ltd.
61
Step 2
Cover a PVC corrugated pipe over the cable parts outside the cabinet and secure the PVC
corrugated pipe to the cable hole.
----End
7.7 Installing Battery Input Power Cables
Procedure
Step 1
Switch all external battery circuit breakers to OFF.
Step 2
Prepare power cables.
1.
Prepare suitable-length cables based on site requirements.
2.
Install an OT terminal on each end of the cables.
Step 3
Install the negative battery string cable at the BAT- screw in the cabinet.
Step 4
Install the positive battery string cable at the BAT+ screw in the cabinet.
Figure 7-19
Installing battery input power cables
(1) Battery switch box