Figure 5-5 Measuring the controller loop voltage
----End
5.4 Initial Configuration
See
.
5.5 Commissioning Procedure
Prerequisites
1. Ensure that the outdoor unit circuit breaker has been switched on before
starting the compressor.
2. Remove the refrigerant steel vessel after checking that no more refrigerant is
required.
3. Users are classified into Admin, Engineer, Operator, and Guest. The Admin
user has the highest permission, followed by Engineer, Operator, and Guest.
The preset passwords are 000001 for Admin, Engineer, and Operator and no
password is needed for Guest. You need to enter Diagnostic Mode as Admin
NetCol5000-A(025, 035) In-row Air Cooled Smart
Cooling Product
User Manual (600 mm Width)
5 Power-On Commissioning
Issue 17 (2020-10-22)
Copyright © Huawei Technologies Co., Ltd.
145