No.
Item
4
The cable ties are evenly spaced. The signal cables are bound neatly with cable
ties to proper tightness, and arranged at even intervals in the same direction.
5
The extra length of the cable ties is cut and removed. The cut surfaces of the indoor
cables are smooth and have no sharp edges.
6
The cable layout facilitates maintenance and expansion.
7
Correct and clear labels are attached to both ends of the signal cables.
lists the checking items for other cable connections.
Table 5-10
Checklist for other cable connections
No.
Item
1
The connectors of the other cables must securely connected.
2
Labels on the cables are legible and bound based on the engineering requirements.
The cables must be bound tightly and neatly. The sheaths of the cables must not
be damaged.
3
Positions for routing the cables must meet requirements of the engineering design.
5.9 Powering on the pRRU
This section describes the power-on check on the pRRU after the pRRU hardware is installed
and checked.
Procedure
Step 1
Optional:
Measure the voltage of the pRRU. This operation is required when AC/DC power
adapter is used.
If...
Then...
The voltage of the AC power adapter
ranges from 100 V AC to 240 V AC (AC/
DC power adapter is used)
Go to
. Otherwise, check for the cause until
the voltage meets the requirement, and go to
Step 2
Power on the pRRU. Wait 3 to 5 minutes, check the status of the RUN indicator on the pRRU.
LampSite
Installation Guide
5 Installing a pRRU