FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
C Installation Verification
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
237
C
Installation Verification
Cabinet Installation Checklist
No.
Check Item
Check Result
1
The cabinet layout is consistent with the equipment room
layout diagram.
□ Compliant □
Incompliant
2
The height deviation of all cabinets and the depth
deviation of adjacent cabinets are less than 5 mm.
□ Compliant □
Incompliant
3
All bolts are tightened, especially the bolts used for
electric connection. Flat washers and spring washers are
installed properly.
□ Compliant □
Incompliant
4
The cabinet is clean.
□ Compliant □
Incompliant
5
The cabinet is clear and complies with dustproof
requirements.
□ Compliant □
Incompliant
6
The paint on the cabinet exterior is intact. If paint flakes
off, repaint that area to avoid corrosion.
□ Compliant □
Incompliant
7
The cabinet door and lock work properly.
□ Compliant □
Incompliant
8
All labels are correct, clear, and complete.
□ Compliant □
Incompliant
9
There is no adhesive tape, cable tie, paper scrap, or
packing material around the cabinet.
□ Compliant □
Incompliant
10
The cabinet filler panels are in proper positions so that
the cold aisle and hot aisle are isolated.
□ Compliant □
Incompliant
Aisle Containment Checklist
No.
Check Item
Check Result
1
All aisle containment components are installed.
□ Compliant □