FusionModule1000A20 CT Solution
Maintenance Guide
2 Operation and Maintenance Preparations
Issue 01 (2019-02-25)
Copyright © Huawei Technologies Co., Ltd.
8
Item
Requirement
Working in the
data center
Only professional personnel are allowed to work in the data center
and only in the presence of designated personnel.
Obtain permission from designated personnel and take necessary
precautions and preventive measures before entering the
FusionModule1000 and performing any operation which may affect
the normal running of the FusionModule1000.
Do not perform any unauthorized operations.
After all work is
finished
Pack up the tools and surplus materials.
Clean up and organize the equipment room environment according
to environment requirements.
Accept the operations and make records about any operations
performed.
Check before
leaving
Check the items to be taken out.
Sign out.
Follow-up
Procedure
Return the ESD clothes and shoes.
If any faulty component is replaced, dispose of the removed faulty
component.
Replace, maintain, and troubleshoot components of the FusionModule1000 only in the
presence of qualified engineers.
2.4 O&M Personnel Skill Requirements
Field
Personnel Skill Requirement
Power
supply and
distribution
system
Familiar with the power supply and distribution system configurations and
the operations for each core component in the FusionModule1000
With power distribution system engineer qualifications
Cooling
system
Familiar with the cooling system configurations and the operations for each
core component in the FusionModule1000
With cooling engineer qualifications
Management
system
With knowledge in the hardware and software of the container data center,
familiar with basic communications protocols, familiar with equipment
interfaces in extra low voltage (ELV) systems, and proficient in operating
the NetEco management system
With ELV engineer qualifications