whether the parameter settings are consistent with the independent
deployment AI_DI unit parameters.
----End
8.1.7.27 How Can I Set and Add a UIM20A Expansion Module (Modbus-TCP)?
Prerequisites
Connect one end of a network cable to the PoE port on the UIM20A expansion
module and the other end to the LAN port on the ECC800-Pro or the PoE port on
the smart ETH gateway.
NO TE
Cascading of UIM20A expansion modules is not supported.
Context
The UIM20A expansion module supports self-discovery and does not need to set
parameters.
Procedure
Step 1 Set the running parameters and control parameters for the UIM20A expansion
module on the WebUI.
1. Log in to the ECC800-Pro WebUI as an administrator.
2. Choose Monitoring > System > UIM Group > UIMn.
3. On the Running Parameters tab page, set UIM20A expansion module
running parameters.
4. On the Controls tab page, set the UIM20A expansion module control
parameters.
----End
8.1.7.28 How Can I Set and Add a Multi-functional Sensor?
If a multi-functional sensor is installed, perform the following steps to configure it.
Prerequisites
One end of the straight-through cable has been connected to the PoE port on the
multi-functional sensor, and the other end has been connected to the PoE port on
the smart ETH converter.
Procedure
Step 1 Set multi-functional sensor parameters.
On the WebUI, choose Monitoring > Aisle > Multi-Func Sensor Group > Multi-
Func Sensor1 > Running Parameters, ensure that Smoke enable and Temp
enable are set to Enable, set High temperature alarm threshold and other
parameters as required, and then click Submit.