Commissioning
Procedure
Description
Automatic software
commissioning
During NodeB software commissioning, the M2000 performs fault
diagnose to ensure that the service check is performed normally. It
is carried out automatically, and you need to focus only on faults.
The M2000 displays all reported alarms on the monitor interface
and provides an easy fault diagnose entry to help you locate faults
fast and provide troubleshooting suggestions.
The software commissioning on the GBTS side involves the sub-
processes. When detecting that the cell initialization of the base
station is complete and there is an available cell for use, the
M2000 proceeds with the next phase automatically.
l
Check cell initialization status of the base station.
l
Query base station information.
l
Check high-precision VSWR. This operation is optional, based
on the setting done when the commissioning task is created.
l
Monitor base station alarms.
l
Check cell serviceability status.
NOTE
In the software commissioning phase, you can view base station alarms and
perform fault diagnose as required, and then take actions accordingly to
solve problems.
Automatic service
check
The M2000 automatically collects the following CS-related and
PS-related counters of the NE to check whether the NE is operating
normally. When non-zero values exist for all the counters, the
service check is passed; otherwise, the service check phase is
always sustained.
Completing
commissioning
After service check is completed, the deployment task state is
displayed as
Confirm Completed Deployment
. After you confirm
that the commissioning task is completed, the M2000 automatically
cancels the
Testing
state of the MBTS and then proceeds with the
site location check.
NOTE
Site location check is the process of checking whether the ESN reported by
the site is consistent with that included in the deployment list. The purpose
is to check for situations where the USB disk is inserted incorrectly in IP
networking mode.
4.6 Monitoring the MBTS Commissioning
This chapter describes how to monitor the MBTS commissioning, thus helping you to obtain
the progress and status of the MBTS commissioning and then rectify faults in real time.
4.6.1 Viewing the Progress and Status of an MBTS Commissioning Task
3900 Series Multi-Mode Base Station
Commissioning Guide
4 Commissioning the MBTS in GU Mode on the M2000
Issue 02 (2010-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4-15