background image

 

 

                                                                             LP-420 REV. 2.14.20 

 

 

SOLAR KIT INSTALLATION INSTRUCTIONS  

FOR VERSA HYDRO COMBINATION APPLIANCES  

(Part # 7100P-220) 

APPLICABLE TO VERSA HYDRO SOLAR MODELS MANUFACTURED AFTER 9/25/2012 

STOP! Follow these instructions or warranty will be void!

 

 

 

This installation shall be done by a qualified service agency in accordance with these instructions, all applicable codes, and 

requirements of the authority having jurisdiction. Failure to follow these instructions could result in substantial property damage, severe 

personal injury, or death. 

INCLUDED IN KIT 

The installation kit includes the following: 

QUANTITY 

DESCRIPTION 

PANEL SENSOR W/ BLACK UV RATED CONNECTION WIRE 

TANK SENSOR W/ GREY CONNECTION WIRE 

FLOW METER 

INSTALLATION INSTRUCTIONS 

Table 1 

TOOLS REQUIRED (NOT INCLUDED) 

  See LP-204 (Versa Hydro Solar Supplement) for a list of tools and materials required in solar installations 

STEP 1: INSTALLATION OF THE SENSORS 

1.  Remove cover from tank sensor opening to expose the stud (Tt). Remove the existing clip and nut. See Figure 1. 

2.  Attach the tank sensor (grey wire) provided in this kit to the stud using the existing clip and nut. See Figure 2. 

3.  Use a drill with ¼” bit to drill a hole in the center of the tank sensor cover. 

4.  Feed grey tank sensor wire through the hole in the center of the tank sensor cover.  

5.  Reinstall tank sensor cover. See Figure 3. 

 

   

    

 

Figure 1 - Tank Sensor Mounting Stud 

 Figure 2 – Installed Tank Sensor               Figure 3 – Wire Fed through Sensor Cover 

6.  Feed wires from tank sensor through the knockout in the lower left of the electronics cabinet. See Figure 4. 

7.  Feed the tank sensor wires through the mounting clip. See Figure 5. 

8.  Attach tank sensor wires to the four position terminal block on the electronics panel at the Tt terminals. See Figure 6. 

NOTE:

 Reverse polarity is not a concern with the sensor wires.  

 

Содержание 7100P-220

Страница 1: ...lement for a list of tools and materials required in solar installations STEP 1 INSTALLATION OF THE SENSORS 1 Remove cover from tank sensor opening to expose the stud Tt Remove the existing clip and nut See Figure 1 2 Attach the tank sensor grey wire provided in this kit to the stud using the existing clip and nut See Figure 2 3 Use a drill with bit to drill a hole in the center of the tank sensor...

Страница 2: ...eed the solar connector sensor wires through a knockout on the right side of the electronics cabinet 11 Connect the panel sensor wires to the SOLAR SENSOR terminals on the customer connection board NHX Models ONLY 1 Connect the NHX pump power leads to the NHX PUMP J3 terminals on the customer connection board See Figure 7 2 Connect the wires from the top sensor of the solar storage tank to the Ts ...

Страница 3: ...nnect the flow meter wire from the customer connection board and install the flow meter as described in the included instruction sheet on the collector supply line pipe running from the Versa Hydro to the solar collector 5 After the flow meter is properly installed feed the flow meter wire through the knockout and reconnect to the customer connection board 6 See Figure 9 for an example of complete...

Страница 4: ...e and cold water inlet of the appliance 3 Gas line must be rated to the maximum capacity of the unit Unit must have 10 feet of pipe after gas regulator 4 All circulators shall have an integral flow check 5 An ASSE 1017 mixing valve is required per SRCC OG 300 6 The flow meter must be properly supported and installed no more than one 1 foot from the Versa Hydro NOTE This drawing is meant to show sy...

Страница 5: ...meters of straight pipe must be installed upstream of all circulators 6 Make sure tank is fully purged of air before power is turned on to the backup heat source 7 Circulators shown in the above hydronic piping should have an integral flow check or alternately use a stock pump with an external spring type check valve Due to extreme temperatures circulators with integral flow checks are not to be u...

Страница 6: ...r inlet of the appliance 3 Gas line must be rated to the maximum capacity of the unit Unit must have 10 feet of pipe after gas regulator 4 All circulators shall have an integral flow check 5 An ASSE 1017 mixing valve is required per SRCC OG 300 6 The flow meter must be properly supported and installed no more than one 1 foot from the Versa Hydro NOTE This drawing is meant to show system piping con...

Страница 7: ...low check remove it 8 Non vertical drain back solar system piping should pitch per foot to facilitate draining 9 No check valves are allowed within the solar loop 10 Solar pumps must be installed 3 below the drain back tank 11 The drain back tank must be properly supported 12 The flow meter must be properly supported and installed no more than one 1 foot from the Versa Hydro STEP 4 PROGRAMMING THE...

Страница 8: ... Volts Range 1 to 10 Volts Table 3 Solar System Parameters STEP 5 SOLAR STATUS MENU The controller also has the ability to review solar system status To access solar status screens press twice Once the first value is displayed press the or keys to access additional information At any point you may press RESET to exit the solar status screens SCREEN DESCRIPTION 0 SOLAR SOLAR 0 FUEL This screen disp...