UPS operations 44
Verifying the REPO port connection
NOTE:
While testing, operate connected equipment in a safe test mode so the effects do not
disrupt critical operations.
After connecting the REPO port (on page
1.
Initiate a REPO by closing the REPO contact.
The Self Test, Battery Fault, Site Wiring Fault, Overtemperature, Overload, and Utility LEDs flash.
CAUTION:
If the polarity is reversed while connecting the REPO port, the UPS powers up
normally.
2.
Verify proper connection of the REPO port:
a.
Power up the UPS ("
b.
Disconnect the REPO port.
c.
Reconnect the REPO port.
If the polarity is correct, the REPO connectors can be disconnected, and then reconnected,
without initiating a REPO.
d.
Verify that the UPS remains in Operate mode (on page
).
e.
If a REPO is initiated, the polarity is reversed. Check and correct the connections.
Powering down the UPS
1.
Shut down all load devices.
2.
Press the Off button to take the UPS out of Operate mode. Power to the load receptacles ceases.
The On Battery LED and Load Level indicator flash.
3.
Disconnect the UPS from utility power.
4.
Wait at least 60 seconds for the UPS internal circuitry to discharge.
Содержание R/T3000 G2
Страница 18: ...Installation 18 ...
Страница 26: ...Installation 26 4 Attach the chassis to the rack using the supplied screws Connecting the battery leads ...
Страница 27: ...Installation 27 Attaching the ERM front bezel ...
Страница 38: ...Installation 38 Installing the extension bars if included ...
Страница 39: ...Installation 39 Connecting and securing the power cords ...
Страница 71: ...Support and other resources 71 ...
Страница 72: ...Support and other resources 72 ...
Страница 79: ...Index 79 W website Hewlett Packard Enterprise 65 weight ERM 60 weight UPS 60 ...