Hardware options installation 88
8.
Install the TPM board. Press down on the connector to seat the board ("
System board components
" on
page
15
).
9.
Install the TPM security rivet by pressing the rivet firmly into the system board.
10.
Install the air baffle.
11.
Do the following:
a.
Install the primary PCIe riser cage (on page
31
).
b.
Install the secondary PCIe riser cage ("
Secondary PCIe riser cage option
" on page
74
).
12.
Install the access panel (on page
25
).
13.
Install the server into the rack ("
Installing the server into the rack
" on page
40
).
14.
Connect each power cord to the server.
15.
Connect each power cord to the power source.
16.
Power up the server (on page
23
).
Содержание ProLiant DL385p Gen8
Страница 6: ...Contents 6 Documentation feedback 132 Index 133 ...
Страница 51: ...Hardware options installation 51 19 Install the air baffle 20 Install the primary PCIe riser cage ...
Страница 65: ...Hardware options installation 65 o 8 or 16 drive SFF o 8 drive LFF ...
Страница 90: ...Cabling 90 Cabling SAS hard drive cabling SFF hard drive cabling SFF cabling with optional drive cage ...
Страница 91: ...Cabling 91 LFF hard drive cabling Optical drive cabling ...
Страница 92: ...Cabling 92 FBWC cabling 8 or 16 drive SFF 8 drive LFF ...
Страница 127: ...Support and other resources 127 ...
Страница 128: ...Support and other resources 128 ...