![HP G2 Series Скачать руководство пользователя страница 39](http://html.mh-extra.com/html/hp/g2-series/g2-series_installation-manual_161557039.webp)
Reference
Item
1
Rack grounding lug
2
M8 Belleville toothed washer
3
M8 flat washer
4
M8 hex nut
The rack grounding lug can be moved to any position on the top or bottom of the rack.
Installing the ground bonding kit on side panels
Procedure
1. Connect a 36.83-cm (14.5-inch) and a 15.24-cm (6-inch) grounding strap with connectors together.
2. Insert a T-25 Torx screw through the end of the 36.83-cm (14.5-inch) grounding strap and secure the screw to the middle
system chassis rail.
3. Place the end of the 15.24-cm (6-inch) grounding strap over the grounding lug on the bottom side panel.
4. Place an M8 internal serrated lock washer and an M8 hex nut over the grounding lug on the bottom side panel and tighten
the washer.
5. Repeat steps 1 through 4 for the other bottom side panel.
IMPORTANT: The location of the welding stud on your model may vary.
Installing the ground bonding kit to the top side panel
Procedure
1. Connect a 36.83-cm (14.5-inch) and a 15.24-cm (6-inch) grounding strap with connectors together.
2. Insert a T-25 Torx screw through the end of a 36.83-cm (14.5-inch) grounding strap, and then secure the screw to the
middle system chassis rail.
Ground Bonding kit
39
Содержание G2 Series
Страница 16: ...Ballast kit 16 ...
Страница 19: ...5 Re attach the front and rear doors Baying kits 19 ...
Страница 26: ...Cable Management Combo kit 26 ...
Страница 29: ...Rack Roof Mount Fan kit 29 ...
Страница 42: ...Hook and Loop Cabling Strap Clip kit 42 ...
Страница 43: ...Hook and Loop Cabling Strap Clip kit 43 ...
Страница 45: ...4 Bundle rack cables as required 1 4 Turn Hook and Loop Cabling Strap kit 45 ...
Страница 57: ...Server Utility Shelf kit 57 ...
Страница 65: ...Side Panel kit 65 ...
Страница 68: ...5 Tighten the bolts from steps 2 and 4 Stabilizer kit 68 ...
Страница 74: ...800 mm rack Universal Rack Tie down kit 74 ...