9.2 Commissioning of the gas burner
■
Open the main shutoff device in the gas supply line.
■
Wait until the gas pressure regulator has reduced the connection pressure to
the set value.
■
Slowly open the cut-off valve in front of the device.
■
Switch on the electric power supply.
■
Set the following on the operating terminal (see operating instructions):
–
'Recirculation' operating mode
–
a room temperature set value that is higher than the current room
temperature (→ heat demand).
■
The operation sequence for heat demand begins. The burner control display
shows the current status:
Display Status
Description
0
Standby
Waiting for heat demand
1
Reset
Software reset
3
Pre-check
Zero position check pressure switch
4
Pre-purge
30 s pre-ventilation by the gas blower
5
Pre-ignition
Ignition without opening the gas valve
6
Ignition
5 seconds of ignition and opening of the gas valve
7
Flame check
The controller checks if a flame is present.
8
Burn
The heater fires up and starts to modulate.
9
Partial load operation
Before the flame stops the burner will modulate to partial
load operation.
10
Burner off
The gas valve closes. The flame stops.
11
Post-purge
Gas blower purges with fresh air. The fan continues to run
to cool down the heat exchanger.
Table 22: Burner control display
28
29
TopVent
®
TG | GV | MG
Operating instructions
Initial commissioning
Initial commissioning
4 220 656-en-03
Содержание TopVent GV
Страница 1: ...TopVent TG GV MG Operating instructions TopVent TG GV MG Original operating manual 4220656 en 03...
Страница 41: ...41 4220656 en 03 Notes...
Страница 42: ...42 4220656 en 03 Notes...
Страница 43: ...43 4220656 en 03...