9 Initial commissioning
Attention
Risk of damage to property as a result of performing initial commissioning
on your own authority. Initial commissioning must be performed by the
manufacturer’s customer service technicians .
9.1 Checklist to prepare for commissioning:
■
Mechanical installation
–
Indoor climate units
– Zone control panels
– Operator terminals
■
Gas installation
–
Gas supply line and gas connection
–
Flue gas evacuation and combustion air supply
–
Compliance with all relevant regulations
–
Approval of the local building authority
■
Electrical installation
–
Power supply for indoor climate units, zone control panels
–
Laying of bus cables conforming to wiring diagram
–
Installation and wiring of all sensors (room temperature sensor, fresh air
sensor, ...)
–
Wiring of external operator terminals
–
Wiring of external inputs and outputs
■
Organisational matters
–
Access to all system components during commissioning (indoor climate
units, operator terminals, ...)
–
Provision of a suitable working platform
–
Organisation of commissioning and training (date, presence of all of the
respective trade groups and of the operating personnel)
The unit is checked at the factory and preset according to the specifications on the
type label.
28
TopVent
®
TG | GV | MG
Operating instructions
Initial commissioning
4 220 656-en-03
4 220 656-en-03
Содержание TopVent GV
Страница 1: ...TopVent TG GV MG Operating instructions TopVent TG GV MG Original operating manual 4220656 en 03...
Страница 41: ...41 4220656 en 03 Notes...
Страница 42: ...42 4220656 en 03 Notes...
Страница 43: ...43 4220656 en 03...