Commissioning of the drive
Read carefully the safety instructions in Chapter 1 and above and follow them.
After the installation:
Check that both the drive and the motor are
grounded
.
Check that the mains and motor cables
comply with the requirements
given in chap-
ter 4.1.1.
Check that the control cables are
located as far as possible
from the power cables,
see chapter 4.3.
Check that the
shields
of the shielded cables are
connected to protective earth
marked with
.
Check the
tightening torques
of all terminals
Check that the
wires do not touch
the electrical components of the drive.
Check that the common inputs of digital input groups are connected to +24V or ground
of the I/O terminal or the external supply.
Check the
quality and quantity
of cooling air (chapter 3.2 and Table 12).
Check the inside of the drive for
condensation
.
Check that all Start/Stop switches connected to the I/O terminals are in Stop-position.
Before connecting the drive to mains: Check
mounting and condition
of all fuses and
other protective devices.
Run the Startup Wizard (see the Application Manual).
6.2
Running the motor
MOTOR RUN CHECK LIST
6.2.1
Cable and motor insulation checks
1. Motor cable insulation checks
Disconnect the motor cable from terminals U, V and W of the drive and from the motor.
Measure the insulation resistance of the motor cable between each phase conductor as
well as between each phase conductor and the protective ground conductor. The insula-
tion resistance must be >1M
at ambient temperature of 20°C.
2. Mains cable insulation checks
Disconnect the mains cable from terminals L1, L2 and L3 of the drive and from the mains.
Measure the insulation resistance of the mains cable between each phase conductor as
well as between each phase conductor and the protective ground conductor. The insula-
tion resistance must be >1M
at ambient temperature of 20°C
Before starting the motor
, check that the motor is
mounted properly
and
ensure that the machine connected to the motor allows the motor to be started.
Set the maximum motor speed (frequency) according to the motor and the
machine connected to it.
Before reversing the motor
make sure that this can be done safely.
Make sure that no power correction capacitors are connected to the motor cable.
Make sure that the motor terminals are not connected to mains potential.