TRANSPORT
HOLZMANN MASCHINEN GmbH www.holzmann-maschinen.at
29
HBS400
TRANSPORT
W A R N I N G
The machine is heavy! For longer transports, disassemble the machine and
transport it in its original packaging if possible!
Observe any instructions and information on the transport packaging with regard to centre of
gravity, attachment points, weight, means of transport to be used and prescribed transport
position, etc.
Before unpacking, transport the delivered product with a lift
truck or stacker to the desired installation site.
The machine is heavy. At least two persons are required for transport and installation.
Never lift the machine by the worktable or by the handwheels, but only by the frame or by the
base where the holes for fixing the machine to the ground are located.
If you transport the machine with a vehicle, ensure that it is protected against slipping, shocks
and vibration.
Assembly
The machine is delivered almost ready for operation. Prior to start-up, the machine must be
secured against tipping over and the following components must be fitted or assembled:
On/Off switch
work table with rip fence and mitre gauge
15.1
Secure bandsaw to the floor
Secure the band saw to the floor at the place of installation using screws
to prevent the machine from tipping over during operation. The machine
base has a total of three through holes (D1,2,3) for this purpose - see
illustration on the left.
15.2
Assembly the worktable
1.
Remove the rip fence guide with scale (1) and the pin
(2).