INSTALLATION
INSTALLATION LOCATION
-
Consult and respect the rules and local regulations which regulate the installation of air conditioning systems.
-
Choose a site without dust and debris.
-
Respect the appropriate service area for the equipment which will be installed.
-
Verify that the ground or structure on which the unit will be installed is able to support its weight in operation.
-
Fit shock absorbers throughout the installation to prevent the transmission of noise and vibration.
-
Check that the direction of the sound level is not going to disturb anyone.
UNIT SETTLEMENT
Make sure that the unit is correctly levelled.
The bed frame should have the area and the strength to support the weight of the unit.
Be sure that after settlement the unit drain is working properly.
SERVICE AREA (mm)
Make sure to respect the following measurements for the correct operating of the unit.
WEIGHT DISTRIBUTION
(kg)
CLVA-BA
1
2
3
4
TOTAL
401
16
20.5
16
20.5
73