3
.
The CBTP start executing.
4
.
Confirm that the test ended and Normal End is indicated in each device.
Figure 8-13 Testing hardware
Note: One full screen may be too small to display all of the device
information.
Verify the results using the
↑
and
↓
keys.
Note: When the abnormal end, Error end, is displayed, consult with Hitachi
Data Systems Customer Support team.
Closing the test program
1
.
Using the
←
and
→
keys, select CLOSE, and then press Enter key. The
window returns to the main menu.
2
.
Select Power Off, and then press Enter key.
3
.
Power Off dialog appears. Select OK, and then press Enter key.
4
.
The CBTP end processing is displayed. When the shutdown process was
successful, the power LED on server blade blinks in green.
5
.
Click File and select Exit.
8-14
Diagnosing server blade
Hitachi Compute Blade 500 Series System Service Manual
Содержание CB 520A A1
Страница 26: ...xxvi Preface Hitachi Compute Blade 500 Series System Service Manual ...
Страница 152: ...4 64 Common process for replacement Hitachi Compute Blade 500 Series System Service Manual ...
Страница 294: ...6 12 Identifying RAID rebuild status Hitachi Compute Blade 500 Series System Service Manual ...
Страница 432: ...9 16 Updating firmware Hitachi Compute Blade 500 Series System Service Manual ...
Страница 439: ...Change LOM configuration 10 7 Hitachi Compute Blade 500 Series System Service Manual ...
Страница 442: ...10 10 Change LOM configuration Hitachi Compute Blade 500 Series System Service Manual ...
Страница 450: ...10 18 Change LOM configuration Hitachi Compute Blade 500 Series System Service Manual ...
Страница 464: ...11 14 Troubleshooting Hitachi Compute Blade 500 Series System Service Manual ...
Страница 465: ...Hitachi Compute Blade 500 Series System Service Manual ...