85
SHINGLES - RIDGE CAP
• You will finish off the top of the roof with a ridge cap made from shingles.
Cut shingles in THREE pieces. Hint: Use cut-off pieces first.
Score shingle,
then snap-off angled cut.
Install first ridge cap flush to shingles at front, as shown.
Install second ridge cap 5" back, as shown.
2
3
BEGIN
1
2"
(5,1 cm)
2"
(5,1 cm)
2"
(5,1 cm)
2"
(5,1 cm)
2"
(5,1 cm)
2"
(5,1 cm)
Top of slot.
Weather Seal
Flush
(1) Nail per side through weather seal.
(1) Nail per side through weather seal.
5"
12,7 cm
FRONT OF
SHED
Flush
10x10'
10x14'
10x18'
27 to 29
Pieces
36 to 38
Pieces
45 to 47
Pieces
Note: • You will need about 27 - 29 cut pieces for 10' x 10' model
• You will need about 36 - 38 cut pieces for 10' x 14' model
• You will need about 45 - 47 cut pieces for 10' x 18' model