4.2.11 Connecting a Halton Safe HSP power unit to the main power supply
WARNING
ELECTRIC SHOCK HAZARD
Before carrying out any electrical work, turn off the power to avoid injury from electrical
current.
NOTICE
NOTICE
All electrical work must only be carried out by qualified personnel.
Note: Do not connect a device that does not have its own fuse to the 24 V AC side of a Halton Safe HSP power
unit.
Connect the wires of the power supply cable to the connectors in the Halton Safe HSP unit.
4.2.12 Connecting the system to the main power supply
Note: Before connecting the system to power, you need to set the addresses of the Halton Safe HSL link units. For
instructions, see
Setting the address of a Halton Safe HSL link unit
.
CAUTION
As the power supply cable also serves as a power strip separator for the controller,
connect the power supply cable into an easily accessible and grounded socket only.
Connect the power plug of the Halton Safe Management 2.0 controller to the socket.
4.3 Checks after installation
Before commissioning can start, make sure the following has been taken care of:
▪ All the components are installed correctly.
▪ All the cabling follows the local regulations and also the cabling requirements listed in
▪ All the wiring is installed correctly.
▪ All the electrical installations have been inspected.