138
3. Installation of valve box
Use parts and components specified for installing the installation components.
Install the lifting tools on the lifting bolts according to the instruction of the Fig.5
Be sure to follow the stipulations on products locally purchased to use nuts (M8 or M10 of 3 pieces for 4 positions)
and gaskets (M8 with the outer diameter of 24~28 mm and M10 with that of 30~34 mm of 2 pieces for 4 positions)
on the upper and lower sides of the lifting tools.
<Note>
Be sure that the product must be installed with the top surface (the oblique surface in the Fig.5) upward, or it will
not work well and increase the working noise.
4. Refrigerant pipe Installation
• Pipes between the outdoor unit and valve box, selection of refrigerant branching suite, and the Pipe between
refrigerant branching suites and the indoor units, please refer to the installation instructions or equipment design
data attached to the outdoor unit.
• Before Installation, make sure the type of the refrigerant to be used is R410A. (If a refrigerant other than this type
is used, It cannot run properly)
• Please provide thermal insulation at the high-pressure gas pipe, suction gas pipe,, liquid pipe and oil equalizing
pipe (pipes for outdoor units in case of multi-split system) and the connections between these pipes. In the
absence of thermal insulation, liquid leakage and scalding may happen. Particularly when the high-pressure
gas pipe delivers indrawn air under full-refrigeration condition, it needs the same thermal insulation as does the
suction gas pipe. Besides, high-pressure gas pipe and suction gas pipe are to deliver high-pressure gas, thus
please provide thermal insulation material that can sustain temperature over 120 °C.
•
Enhance the thermal insulation material based on the installation environment. The indicators are shown below.
For RH75%–80% at 30°C: over 15 mm thick.
For over 80% at 30°C: over 20 mm thick.
If not reinforced, the thermal insulation material surface is prone to condensation. Please refer to the equipment
design data for further details.
Nut
(purchased locally)
Valve box
Lifting bolt
(purchased locally)
Double nuts
(purchased locally)
10-15mm
Lifting tool
Gasket
(purchased locally)
Fig.5
Install the valve box in a level orientation.
Install the valve box in an orientation so that
the drain pipe side is higher may result in
water leak-age.
Drain
socket
With 1°
Valve box
Wrong
installation
Valve box
Drain
socket
Proper
installation
Содержание MRV 5-RC AB052MAERA
Страница 1: ...MRV 5 RC Service Manual SYJS 03 2019REV A Edition 2019 03 ...
Страница 3: ......
Страница 55: ...52 AV08 10 12 14IMVURA 4 Center of gravity x X 347 9587 y 471 5454 z 725 6683 y z ...
Страница 56: ...53 AV16 18 20 22IMVURA x X 650 5962 y 380 7255 z 706 5342 y z ...
Страница 106: ...103 2 Dimension 4 19 200 60 25 25 25 249 108 232 84 69 388 73 82 65 103 177 4 44 4 35 277 ...
Страница 116: ...113 2 Preparation before installation ...
Страница 130: ...127 2 Dimension 290 67 410 220 567 137 160 189 57 144 109 159 159 212 393 4 22 65 65 65 65 65 44 65 76 4 52 67 156 830 ...
Страница 162: ...159 One by one valve box PCB code 0151800186A 2 Valve box PCB photo and dip switch setting ...
Страница 165: ...162 One by four valve box PCB code 0151800466 ...