136
1. Pre-installation
The installation location selected shall meet the following conditions and be approved by users.
• The strength shall be sufficient to withstand the weight of the valve box
• There is no significant tilt on the plane.
•
Ensure that there is enough space for installation and maintenance.as show in Fig.1
•
There is space for inspection on the side and top of the electric box
•
The length of piping between the indoor and outdoor units shall be within the permissible range (referring to the
specification attached to the outdoor unit).
• Please install the valve box in places where noise will not influence the customers too much (such as washroom,
passageway, warehouse, equipment room, etc.). Places with high requirement for quiet are not suggested for
installation, such as bedroom, drawing room, meeting room, office, etc.
Note:
•
the electrical box can be changed as show in 3 valve box installation.
• When starting up, stop, defrosting, and oil-returning in heating mode , the 4-way valve will veer and create noise.
This kind of noise is normal for the running of valve box.
•
A noise may be emitted by the valve box as aresult of control during operation or stopping of an indoor unit. If it is
installed in the ceiling where it is exposed, take adequate precautions with the installation location.
<Notice item>
• Inspect whether the installation location can sufficiently withstand the weight of valve box and set the hoisting
bolts by reinforcing the beam if necessary. Use hoisting bolts in installation (referring to 2 for the preparation
before installation).
•
Install the power wiring and power line of the valve box at more than 1 m away from TV and radio to prevent the
image clutter and noise. But, there may be noise even if it is more than 1m according to the different waves.
Indoor unit
side pipe
Drain socket
Electrical box
Manhole must be arranged on
the side of the electrical box.
500
500
Fig.1
Outdoor unit side
(3 pipes)
Outdoor unit side
(3 pipes)
100 or more
100 or more
Dooryard
300 or more
500 or more
Содержание MRV 5-RC AB052MAERA
Страница 1: ...MRV 5 RC Service Manual SYJS 03 2019REV A Edition 2019 03 ...
Страница 3: ......
Страница 55: ...52 AV08 10 12 14IMVURA 4 Center of gravity x X 347 9587 y 471 5454 z 725 6683 y z ...
Страница 56: ...53 AV16 18 20 22IMVURA x X 650 5962 y 380 7255 z 706 5342 y z ...
Страница 106: ...103 2 Dimension 4 19 200 60 25 25 25 249 108 232 84 69 388 73 82 65 103 177 4 44 4 35 277 ...
Страница 116: ...113 2 Preparation before installation ...
Страница 130: ...127 2 Dimension 290 67 410 220 567 137 160 189 57 144 109 159 159 212 393 4 22 65 65 65 65 65 44 65 76 4 52 67 156 830 ...
Страница 162: ...159 One by one valve box PCB code 0151800186A 2 Valve box PCB photo and dip switch setting ...
Страница 165: ...162 One by four valve box PCB code 0151800466 ...