Information for electricians
Commissioning and performing a functional test
11
31
33
32
32
9
Fig. 9: Mounting of water leakage sensor
31
Water leakage sensor plug
32
Water leakage sensor
33
Connection socket for additional water leakage sensors
Testing of water leakage sensor
1
Place a moist cloth on the water leakage sensor.
Cookguard triggers test alarm
2
After a successful test, dry and clean the water leakage sensor.
5.2
Commissioning and performing a functional test
A functional test should be carried out by an electrician after installation.
The default settings of the cookguard are to be used for the initial commissioning. If the installation
height of the sensor unit or the dimensions of the cooker/hob deviate from the standard values (Bild 8),
then commissioning must be carried out manually (see Manual commissioning).
Performing a functional test
1
Switch on cooker/hob with highest power.
With an induction cooker, a suitable pot must be used for commissioning.
2
Keep the OK button (3) pressed for 5 s.
The power supply to cooker/hob is interrupted. Cooker/hob is switched off.
3
Check if cooker/hotplate is switched off.
4
Switch off cooker/hob manually via the corresponding hotplate switch.
5
With the cooker/hob switched off, press the OK button (3) once.
The power supply to the cooker/hob is switched on again. Cookguard is ready for operation. Sta-
tus LED (5) flashes once in green.