Verifying the installation
Table 6 Post-installation checklist
Item
Requirements
Installation site
•
No condensation on the surface of the gateway or inside of the gateway.
•
Keep the gateway clean and dust free.
•
No packing boxes, packing bags or other packing materials left in the installation
site.
•
Keep the air inlet and outlet vents of the gateway free of obstruction.
Gateway
•
All modules are installed correctly.
•
No slot is empty. Each is installed with a module or filler panel,
•
Fan trays are installed correctly.
Cables
•
The gateway is grounded reliably with the provided grounding cable. Both ends of
the grounding cable are securely connected.
•
No switch or fuse is installed on the grounding cable.
•
The power cords are connected reliably and no short circuit has occurred in power
input and output.
•
Power cords, grounding cables and fiber cables are routed and bound separately.
•
The cables are bound neatly with cable ties at an even distance.
•
The cable labels are correct, clear, and affixed to the cable in the same direction.
Electricity safety
•
A circuit breaker is provided for each power input line.
•
The circuit breaker is switched off before you connect the power cord to a power
module,
Power-on check
WARNING!
Locate the emergency power-off switch in the room before power-on so you can quickly shut power
off when an electrical accident occurs.
CAUTION:
Before powering on the gateway, make sure all fan trays are present.