background image

2

QUICK REFERENCE GUIDE

STEPS 1-5 INSTALLATION

1

Take out each of the items 
included in the sales kit. 

Note that low voltage sales 
kit GLD-GO-LV includes gate 
transformer (MGTR3-120VA).

INSTALLING THE BASE MOUNTING PLATE 

2

1.  Position the base mounting plate as required, referring to the planning section (figure 1).
2.  Mark and drill the four masonry anchor holes (figure 2).

NOTE: Position the power cord through the base mounting plate before mounting the base plate.

3.  Mount the base mounting plate to the ground or concrete pad using the four masonry anchors provided. 

NOTE: Ensure the base mounting plate is orientated in the correct way. The arrow on the base mounting plate needs to be set 
towards the gate.

figure 2

1.  Manually move the gate into OPEN position.
2.  The nylon rack can be attached with screws. Put the first rack segment at the end of the gate so that it rests on the opener drive 

sprocket (figure 1) and attach the rack to the gate (figure 2).

3.  Move the gate and attach the next rack segment near to the previous segment. Proceed this way until you will reach complete 

CLOSED position. 

NOTE: If the rack is already fixed to gate, it may be required to adjust the height of the gate opener to ensure correct 
engagement of the drive gear with the gate rack.

figure 1

figure 2

GATE RACK MOUNTING

3

Manual

Quick 

Reference

Guide

2 x Release
Keys

Quick
Reference 
Guide

2 x Limit Switch
Brackets

4 x M8 x 80mm
Masonry Anchors

4 x M8 x 40mm
Bolts with hexagon
nuts & plain washer

Instruction 
Manual

Gate Transformer
240V -24V 120VA
MGTR3-120VA

4 m Slide Gate Rack

Base Mounting Plate

2 x 4 Channel
Transmitters

Opener (GLD-GO or
GLD-GO-LV)) 

Underneath the 
mounting plate
is the concrete 
slab

Mounting
plate

90 - 100mm

Rack

figure 1

Отзывы: