Model IGX Make-Up Air
13
®
3. Install Ductwork
Follow good duct practices for all ductwork. Install
ductwork in accordance with SMACNA and AMCA
guidelines, NFPA 96 and local codes. Reference
Installation, Duct Sizes
section in this Installation,
Operation, and Maintenance Manual for proper
duct sizes.
The use of a duct adapter is recommended on a
downblast (DB) arrangement to align the ductwork with
the supply unit. The duct adapter is only a guide and is
not to be used as a support for the ductwork.
Supply
Ductwork
by Others
Exhaust
Ductwork
by Others
Ductwork
4. Apply Sealant
Apply an appropriate sealant around the perimeter of
the curb and duct to isolate unit vibration and prevent
water penetration.
Supply Duct with
Duct Adapter Installed
Exhaust Duct Installed
Sealant
Sealing Ductwork
Installation
Outdoor Unit Mounting
Combination Curb
(continued)
6. Install Exhaust Fan Options
Install hinges (an optional hinge kit is available from
manufacturer) with restraining cables and optional
grease trap with drain connection.
7. Install Supply Unit
Use a crane and a set of spreader bars hooked to the
factory lifting lugs to lift and position the unit on the
curb extension and equipment support(s). The use of
all lifting lugs and a set of spreader bars is mandatory
when lifting unit.
Fasten the unit to the curb extension and equipment
support(s) using appropriate methods. The installer
is responsible for determining appropriate support
and fastening methods to ensure compliance with all
applicable codes.
Exhaust Fan
Installing Exhaust Fan
5. Install Exhaust Fan
Fasten exhaust fan to curb extension using appropriate
methods. Installing the exhaust fan prior to the
supply unit will allow for easier installation of options.
NFPA 96 requires the exhaust fan to be hinged. Follow
instructions included with the exhaust fan.
Installing Supply Unit