G4130 NO
x
/O
2
Analyzing System
9
3
System Installation
Read this chapter in its entirety before installing the system.
3.1
Control at Delivery
When you receive the G4130 NO
X
/O
2
Analyzing System, please inspect and con-
firm that the received items are in accordance with the packing list and not dam-
aged. Any discrepancy should be reported to the supplier immediately. If any of
the received parts are damaged, the shipping company should be informed and
new parts should be made available before completing the installation.
3.2
Where to Install the System
Satisfactory operation, faultless functions, and minimal maintenance of the G4130
NO
X
/O
2
Analyzing System are achieved by paying attention to the following
points:
Make sure to install the probe in a suitable location where it will extract
the gas that is going to be tested.
The probe shall be fitted at least 10 pipe diameters after the outlet of the
engine, the turbocharger, or the last after-treatment device – choose which-
ever is further downstream. However, the probe shall also be placed at
least 0.5 m or 3 pipe diameters upstream from the exit of the exhaust gas
system – choose what provides the greatest length. See Figure 3-1 and
Figure 3-2
for the installation layout of the probe. If you find it difficult es-
timating where to install the probe, please contact Green Instruments A/S
for more instructions.
As a standard scope of supply, the analyzing board can be installed up to 3
m from the probe. If necessary, the umbilical cord can be extended.
Содержание G4130 NOX/O2
Страница 1: ...PART NUMBER 02156 G4130 NOX O2 ANALYZING SYSTEM WITH DIFFUSION PROBE MANUAL...
Страница 2: ......
Страница 3: ...Version 1 1 Revision Jan 2019 Part nr 02156 2...
Страница 17: ...System Installation Version 1 1 Revision Jan 2019 Part nr 02156 16 Figure 3 7 Analyzing board dimensions...
Страница 18: ...G4130 NOx O2 Analyzing System 17 Figure 3 8 Piping and connection diagram...
Страница 30: ...29...
Страница 31: ......