3.Installation
3-5 Installation of the water pipes
1)To reduce the resistance of the water pipe as much as possible , reducing the elbow position and
variable diameter can be adopted.
2) In the process of the piping connection, please make sure the whole system to be clean, no rust
and no other dirt, in order to prevent the piping blockage.
3) Leak test should be done after the piping connection is finished. The test should focus on the
screw thread connection to ensure the whole system without leakage, then thermal insulation
should be done.
4) After all the piping are connected and tested leakage, 20mm thick thermal insulation must be
packed on the piping in order to reduce the heat loss and prevent the water pipe freezing in winter.
5) Expansion tank needs to be installed in the highest point of the water circuit. The
water level of the expansion tank should be at least 0.5 M higher than the highest point.
6) Check the water flow of the water circuit system to ensure the normal water flow rate. If there is
water flow fault, check the installation of the water circuit system. In order to make sure the
protection on the unit when the system has no water, do not bridge the water flow switch casually.
7) Auto vent valve should be installed in the highest point of the water circuit, to prevent the air
trapping which will affect the operating effect.
8)Thermometer and pressure gauge should be installed for the water inlet and water
3-6 Water injection and evacuation
1) Vent valve needs to be installed in the highest point of the water circuit system and drain valve
needs to be installed in the lowest point of the water circuit system.
2) When the installation is finished, please keep the power supply off.
3) When the inlet valve is opened, the water injection begins. At this time, please keep the vent
valve open, the air in the system will evacuated via the vent valve outlet, and there is sound “tehee”
from the vent valve.
4) Double check all the connections and elbows of the water circulation system, make sure there is
no leak.
5) If there is no leak, then start the water pump to run the water circuit and double check if there is
leak from the connections and elbows.
6) When the sound “tehee” disappears from the vent valve, the water injection is finished and water
pump can be stopped, then prepare to energize the unit and start it.
Содержание ANTEK AIR MAGNA 100
Страница 8: ...AIR MAGNA 100 GREEN ENERGY SYSTEMS 8 3 Installation 3 4 The space of installation and maintenance...
Страница 15: ...AIR MAGNA 100 GREEN ENERGY SYSTEMS 15 4 User instruction...
Страница 16: ...AIR MAGNA 100 GREEN ENERGY SYSTEMS 16 4 User instruction...
Страница 17: ...AIR MAGNA 100 GREEN ENERGY SYSTEMS 17 4 User instruction...
Страница 28: ...AIR MAGNA 100 GREEN ENERGY SYSTEMS 28 8 Wiring diagram...
Страница 33: ...AIR MAGNA 100 GREEN ENERGY SYSTEMS 33 Note...