PART 2 COMMISSIONING PROCESS
NOTICE
!
①
It is forbidden to directly connect the compressor with power supply and forcibly power it on
during commissioning and maintenance.
②
Engineering commissioning operations must be performed on the Ultra Heat GMV serial unit.
Otherwise, the unit cannot properly run.
③
Before commissioning is completed, the main board of ODU displays "A0" and that of IDU
displays
―A0‖.
④
A module must be set to master module and only one can be set during commissioning.
⑤
An IDU must be set to master IDU and only one can be set during commissioning for heat pump;
And for heat recovery VRF, there is no need to set master IDU.
⑥
Other functions can use the factory settings if there are not special engineering requirements.
1 NECESSITY OF VRF ENGINEERING COMMISSIONING
Different form ordinary air conditioning units, the VRF system raises high design requirements and
easily incurs operation-affected factors such as impurities and water during engineering installation. Due
to the requirements on engineering design/installation complexity and high-precise system control,
commissioning is mandatory after engineering installation. Only a qualified unit can be delivered for use.
2 REQUIRED FILES AND TOOLS FOR ENGINEERING DEBUGGING
2.1 Required Tools for Engineering Commissioning
Inner hexagon spanner
Digital thermometer
Shifting spanner
Noise meter
Cross screwdriver
Clamp meter
Straight screwdriver
Digital multimeter
Vacuum pump
Electricity meter
Electronic balance
Timer
System high and low pressure gauges for corresponding
refrigerants
Step ladder
Wind-speed transmitter
…
The Ultra Heat GMV provides two commissioning methods. One is to perform commissioning by
pressing buttons on the main board of ODU. The other is to perform commissioning on a PC through
professional software. Parameters of the ODU and IDU can be simultaneously displayed with the second
method. (For details about these methods, refer to respective instructions.)
2.2 Commissioning Files
The following commissioning files are required to record installation and commissioning of units:
pre-commissioning scheme determination meeting minutes, commissioning personnel record tables,
commissioning system appearance check record tables, commissioning data record tables, and
Содержание Ultra Heat GMV-VQ72W/A-F
Страница 1: ...Ultra Heat GMV Multi VRF TECHNICAL SERVICE MANUAL R410A Heat Recovery Series ...
Страница 26: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial INSTALLATION 22 CHAPTER 2 INSTALLATION ...
Страница 30: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial INSTALLATION 26 ...
Страница 73: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial INSTALLATION 69 ...
Страница 120: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 116 CHAPTER 4 MAINTENANCE ...
Страница 135: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 131 ...
Страница 136: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 132 2 System high pressure protection E1 ...
Страница 137: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 133 3 System low pressure protection E3 ...
Страница 167: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 163 PFC board Drive board ...
Страница 203: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 199 5 4 NCHS4B U ...
Страница 205: ...Ultra Heat GMV VRF Technical Service Manual_Heat Recovery Serial MAINTENANCE 201 5 5 NCHS8B U ...
Страница 207: ...Jf00303410 ...