65
Test Operation, Troubleshooting and Maintenance
◆
Check for a single unit
(1) Co
mmission one single unit first and stop all others.
(2)
Do the compressor, fans and the 4-way valve run normally without any unusual noise?
(3)
Is the voltage phase difference lower than ±2%?
(4)
Voltage phase difference =(phase difference between the max and average voltage)/(average
voltage)×100%.
(5) Start up this single unit.
(6)
Do its compressor, fans and the 4-way valve run normally without any unusual noise?
(7)
Check other units one by one in the same way.
◆
Check for the water flow of a single unit
In order to prevent the water temperature changing too quickly, it is suggested to open all terminal
units in commissioning, and observe and record the pressure drop of the manometers at the outlet
and inlet pipes. Also, adjust the flow control valves or shut-off valves to make the flow meet application
requirements.
When the environmental temperature is available, let the unit perform cooling (>15°C). When the unit
has run stably for 10 minutes, the normal difference of the entering and leaving water should be 4-6°C.
(1) If the temperature difference is larger than 4-6
°C, raise it by reducing the water flow of other units.
(2) If the temperature difference is smaller than 4-6
°C
, ignore it in the event that the difference of other
units is suitable, and reduce the water flow of this unit in the event that the difference of other units
is also unsuitable.
(3) Check f
or the water flow of other units one by one in the same way.
◆
Check for operation of the whole unit
(1) Check
the difference of the entering and leaving water temperature of each unit when the whole
unit has been in operation. If temperature adjustment fails, reconsider the capacity of the selected
water pump.
(2)
Start up the whole unit under the full load. When the whole unit has run stably for one hour, check if
the water temperature and the air conditioning effect meet the user’s requirements.
(3)
Observe and record the entering and leaving water temperature, condensing and evaporating
pressure. Then, stop the unit and check the setpoint of each parameter on the control panel. After
that, complete the commissioning date sheet.
(4) When the unit comes to the protection state, diagnose it and and seek solutions.
Содержание LSQWRF35VM/NaA-M
Страница 1: ...Service Manual Change for life A series modular air cooled chiller heat pump T1 R410A 50Hz T1 R32 50Hz...
Страница 5: ...1 Product Product...
Страница 18: ...14 Unit Control Unit Control...
Страница 29: ...25 Unit Installation Unit Installation...
Страница 58: ...54 Unit Installation 3 5 7 Electric wiring digram 1 LSQWRF35VM NaA M...
Страница 59: ...55 Unit Installation 2 LSQWRF60VM NaA M LSQWRF65VM NaA M...
Страница 60: ...56 Unit Installation 3 LSQWRF35VM NhA M...
Страница 61: ...57 Unit Installation 4 LSQWRF60VM NhA M...
Страница 62: ...58 Unit Installation 5 LSQWRF130VM NhA M...
Страница 63: ...59 Unit Installation...
Страница 64: ...60 Unit Installation The electric wiring diagrams on the unit always prevail...
Страница 66: ...62 Test Operation Troubleshooting and Maintenance Test Operation Troubleshooting and Maintenance...