4. 

Technical data 

 
 

5. 

Assembly 

5.1 

Trial installation 

The container should be assembled on a trial basis before the final assembly to determine the position 
the following connections: 

 

Inlet 

 

Overflow 

After opening the connections it is important to remove and clean all the drilling and sawing swarf from 
the tank. 

 

5.2 

Tank assembly 

The tanks consist of two identically constructed halves. For the assembly, the half with 
the closed side is positioned on the compacted and level ground surface. The profiled 
sealing ring is then well coated with lubricating soft soap and pressed with the ribbed 
side into the continuous perimeter of the inner seat recess. Before the second half of 
the tank is set in position, the seal and the seat recess of the upper half must also be 
well coated with the lubricating soft soap. During the assembly it is important to ensure 
that the seal does not slip out of the seat recess. 

To secure the two halves, the connection clips are fitted first in a counter-
clockwise direction and then in a clockwise direction. To assist in the 
assembly it may be necessary to press the two tank halves together with a 
number of G-clamps. To do this, position 3 to 4 G-clamps at equal intervals 
around the lip of the tank and then begin to tighten them evenly.  Finally 
position the connection clips by hand and then drive them securely into place 
using a hammer with a piece of wood in between, the clips will then locate in 
the final engaged position. 

Marking upper tank half 

Marking lower tank half 

Содержание RainHarvest Systems Top-Tank 323002

Страница 1: ...g Any missing instructions must be requested directly from us A complete check of all the items components for possible damage must be carried out before the assembly or installation begins The installation must be carried out by a professional firm Table of Contents 1 GENERAL NOTES 2 1 1 Safety 2 1 2 Identification obligation 2 2 INSTALLATION SET UP REQUIREMENTS 2 2 1 Assembly above ground 2 3 TR...

Страница 2: ...an accidental connection to the drinking water network even after years Even when there are correct labels irritations are possible e g through children That is why all tapping points of process water have to be installed with child proof valves 2 Installation set up requirements 2 1 Assembly above ground The tanks must be installed on an appropriate level and compacted surface that is free from s...

Страница 3: ...f the inner seat recess Before the second half of the tank is set in position the seal and the seat recess of the upper half must also be well coated with the lubricating soft soap During the assembly it is important to ensure that the seal does not slip out of the seat recess To secure the two halves the connection clips are fitted first in a counter clockwise direction and then in a clockwise di...

Страница 4: ... into the tank at least 20 cm If more than two tanks are to be connected to one another then in addition to the lower connection inlet there must also be an upper connection to ensure ventilation 6 2 Laying connections The connection of the inlet and overflow is by means of the pre drilled openings of the tank or by means of the pre molded connection points intended for opening All the suction and...

Отзывы: