Tighten the lock nut (3).

 

The adjustment is finished. 

 

3.9

 

PIPE RUPTURE VALVE (VC) TEST (IN THE VALVE BLOCK) – N° 5 

 

 

WARNING 

Before doing this test, the pipe rupture valve mounted on the piston should be adjusted (refer to VC 
manual)  

 

Send the car with full load to the highest floor. 

Once the car has stopped. 

Loosen the lock nut (5) to test the rupture valve 

Completely tighten the screw n.5 . 

Call the car to the lowest floor. 

The test is finished. 

 

 

NOTE:

WHEN THE CAR DOWNWARD SPEED MATCHES THE INTERVENTION FLOW,THE 

RUPTURE VALVE CLOSES TO STOP THE CAR (IN CASE OF BY-PASS RUPTURE VALVE,THE 
CAR LOWERING CONTINUES SLOWLY).IN CASE THE RUPTURE VALVE DOES NOT 
CLOSE,FOLLOW THE FACTORY INSTRUCTIONS TO REDUCE ITS INTERVENTION SPEED TO 
BE ABLE TO RESTART THE TEST.

 

 

Completely loosen the n.5 . 

During the standard car downward we do not have any intervention of the rupture valve 

Completely tighten the lock nut (5). 

The test is finished. 

 

3.10

 

ADJUSTMENT OF THE MINIMUM RAM PRESSURE, VSMA (2:1 SYSTEMS) N° 6 

 
Only in installations with traction 2:1. 

Close the ball valve (S).

 

Press the manual lowering button (MM) to release pressure. 

Check the pressure on the manometer (MAN) is around 6 bar.  

If the pressure it not correct, adjust screw (6). 

The adjustment is finished. 

 

3.11

 

MANUAL  LOWERING  OPERATION (EMERGENCY ONLY) – BUTTON  (MM) 

 

Press the manual lowering button (MM) to send downward the car to the unlock door area 

 

3.12

 

ADJUSTMENT OF THE MAXIMUM PRESSURE - HAND PUMP 

Close the ball valve (S).

 

Verify that the suction tube is immersed in the oil.

 

Loosen the screw (V) two or three turns to bleed the air.

 

Push the lever several times till the oil starts flowing through the 

screw (V).

 

Tighten the screw (V) completely.

 

Loosen the lock nut (10)

 

Loosen the screw (10) two or three turns.

 

Open the shut-off valve for pressure gauge exclusion (RUB).

 

Push the hand pump lever to reach the maximum pressure, 

adjust the screw (10) till the value is 2,3 times the full load 
pressure (refer to the lift technical report). 

 

Example

If full load pressure is 35 bar, screw (10) should be adjusted to: 

      35 x 2,3 = 80,5 

When the pressure is correct. 

Tighten lock nut (10). 

Open the ball valve (S). 

The adjustment is finished. 

 

 

 

Содержание 3010

Страница 1: ...ND COMPONENTS FOR LIFTS UNI EN ISO 9001 Certified Company 1 01 ENG English 3010 VALVE SELL TECH WORK CUST USER 3010 VALVE MANUAL INSTALLATION USE AND MAINTENANCE 1 0991 497 EN AVAILABLE WITH TANK TYPE HL HL DRY HL 50 DRY HLV HLV 40 e GL ...

Страница 2: ...3 3 ADJUSTMENT OF THE UPWARD ACCELERATION N 4 10 3 4 ADJUSTMENT OF SLOW LEVELLING SPEED N 2 10 3 5 ADJUSTMENT OF THE UPWARD HIGH SPEED N 8 10 3 6 ADJUSTMENT OF THE DOWNWARD ACCELERATION N 7 10 3 7 ADJUSTMENT OF THE DOWNWARD HIGH SPEED N 9 10 3 8 ADJUSTMENT OF THE UPWARD AND DOWNWARD DECELERATION N 3 10 3 9 PIPE RUPTURE VALVE VC TEST IN THE VALVE BLOCK N 5 11 3 10 ADJUSTMENT OF THE MINIMUM RAM PRES...

Страница 3: ...ressure adjustment 7 Downward start adjustment 8 High speed adjustment 9 Down speed compensator empty full load 10 Hand pump max pressure adjustment 11 Minimum upward pressure adjustment RUB Shut off valve for pressure gauge exclusion MAN Pressure gauge MM Manual lowering button PAM Hand pump V Hand pump air purge screw VP Pilot valve CHK Check valve VMD Downward solenoid valve VML Jump speed sole...

Страница 4: ...the documentation shouldn t be damaged and shouldn t have missing parts Moreover do not tear or deteriorate sheets during consulting 0 3 SAFETY PRECAUTION DURING INSTALLATION WARNING Before starting all kind of installation operation ALWAYS verify that all the safety devices mechanical or electrical are active and working properly 0 4 TOOLING Use standard building yard tooling for the installation...

Страница 5: ...LATION In these instructions the major points concerning the safety and prevention will be marked with the following symbols General warning Warning high risk of danger Risk of injury e g crushing sharp edges protrusions etc Warning risk of electrical damage exposed parts Beyond the instruction manual it should take into account national standards laws regulations and other rules on accident preve...

Страница 6: ...ting the different working procedures and therefore do not take any action without first considering the consequences Make sure that the products received are complete with everything you need and that all products and parts are not damaged during transport Data written on the label should be compared with the order form During the storage period keep the material in the original container protect...

Страница 7: ...Screw for rupture valve test EN 81 20 6 Minimum ram pressure adjustment 7 Downward start adjustment 8 High speed adjustment 9 Down speed compensator empty full load 10 Hand pump max pressure adjustment 11 Minimum upward pressure adjustment RUB Shut off valve for pressure gauge exclusion MAN Pressure gauge MM Manual lowering button PAM Hand pump V Hand pump air purge screw VP Pilot valve CHK Check ...

Страница 8: ... all electrical power by opening the main switch Power wires must be of sufficient section to support the required current and appropriate insulation for the voltage of the mains Wires must not come in contact with hot parts The ground wire should always be connected to the screw marked with the appropriate symbol 2 6 CONNECTION BOX Power units with immersed motor have the motor connection box loc...

Страница 9: ...de the pipe as this may cause a damage to the gaskets seals of the piston and the valves jeopardising the correct functionality of the system Remove the nut and the compression fitting ring from the silencer joint Insert the compression fitting ring as shown in the figure Make sure that the silencer joint is tight Clean and apply a thin layer of oil to the thread and the joint area Insert the tube...

Страница 10: ...DJUSTMENT OF THE UPWARD HIGH SPEED N 8 Start to send the car upward Loosen the lock nut 8 Tighten the screw 8 till you hear the oil returning to the tank then loosen one turn to close Tighten the lock nut 8 The adjustment is finished If needed in those lifts where the speed must be limited for example Home Lift con V 0 15 m s other lifts just gradually tighten the screw 8 to mach the requested spe...

Страница 11: ...ADJUSTMENT OF THE MINIMUM RAM PRESSURE VSMA 2 1 SYSTEMS N 6 Only in installations with traction 2 1 Close the ball valve S Press the manual lowering button MM to release pressure Check the pressure on the manometer MAN is around 6 bar If the pressure it not correct adjust screw 6 The adjustment is finished 3 11 MANUAL LOWERING OPERATION EMERGENCY ONLY BUTTON MM Press the manual lowering button MM ...

Страница 12: ... of the oil 6 Motor protection operation 6 Filters 1 Pressure check 6 Pressure gauge shut off 6 6 Pressure test static pressure x2 6 Ball valve seal 6 Labels signs and schemes 6 Overall check up 5 4 3 MAINTENANCE OPERATIONS What to do Valve gaskets seals At the end of installation and during check ups verify the gasket seals in the following way with the oil at room temperature close the ball valv...

Страница 13: ...se the ball valve S again Continuing with the hand pump reach the desired pressure value controlling with the pressure gauge After the test completely unload the pressure pushing with a screwdriver on the VMD valve Close the pressure gauge exclusion valve Disconnect the hand pump Screw the pressure gauge MAN Ball valve seal Close the ball valve S and open the pressure gauge shut off RUB Fully disc...

Страница 14: ...ward speed is less than the upward speed DEVICES VRF VMD COMPENSATOR VRF Check the adjustment of the screw 8 VMD Check the cleanliness of filters and restrictors SPEED COMPENSATOR Check the perfect sliding of the spool If it s necessary tighten the screw 9 to increase downwards speed The lift only runs at high speed both upward and downward DEVICES VML VRF VML Check that the screw 3 is open Clean ...

Страница 15: ...ENG 1 01 1 0991 497 EN 24 03 2017 15 16 3010 VALVE MANUAL INSTALLATION USE AND MAINTENANCE ...

Страница 16: ...NCE 16 16 Doc n 1 0991 497 Rev 1 00 24 03 2017 File 3010 3_4_10991497EN doc FLUID DYNAMICS EQUIPMENTS AND COMPONENTS FOR LIFTS UNI EN ISO 9001 Certified Company GMV SPA Via Don Gnocchi 10 20016 PERO Milano Italy TEL 39 02 33930 1 FAX 39 02 3390379 http www gmv it e mail info gmv it ...

Отзывы: