INSTALLATION GUIDELINES 

RECEIVING AND UNLOADING 

Unload panel crates/pallets with appropriately sized equipment to avoid 
damage to the panels contained within.  Extended reach forklifts may be re-
quired depending on the crate/pallet size.  Additional equipment may be 
needed if unloading with an overhead crane, or other equipment, in order to 
avoid damage to the product.  Always use a spreader bar and slings in order 
to avoid crushing the crates. 

Inspect all crates/pallets for any damage prior to unloading.  Report any damage to the freight carrier, docu-
ment the damage on the bill of lading and immediately report the damage to CMG.  The receiving party must 
make all claims for any damage directly to the freight carrier upon receipt.  CMG is not responsible for any 
damage after the product leaves the factory.  The customer is responsible for filing a freight claim for any 
damage directly with the freight carrier within 24 hours of receipt.  Failure to do so may result in the loss of 
the right to receive corrective action. 

 

After unloading, open each crate and verify that the contents matches the attached packing list.  Notify your 
CMG representative of any mismatches within 24 hours.  Failure to do so may result in the loss of the right to 
receive corrective action. 

 

STORAGE AND HANDLING 

Store crates/pallets in a clean and dry location, and keep them protected from all outside elements and se-
vere conditions.  Avoid storing or carrying panels in a flat orientation.  Always store and move panels in a ver-
tical position. 

 

INSTALLATION 

Inspect all areas that will receive the panels and ensure that all substrates and underlying requirements are 
in place and that all surfaces are acceptable for proper panel installation.  Do not begin installation until all 
conditions are acceptable.   

 

Reference the approved shop drawings and locate the principal components for panel system alignment, 
such as doors, windows, corners, soffits or other items that are critical in determining joint locations.  Snap 
chalk lines in order to ensure that all installation lines are level and plum, and conform to the layout shown on 
the approved shop drawings. 