1. Intended use

The product is applicable for liquids with specific conductivity over 10 µS/cm. The 
switching unit can sense the resistance between probes. Conductivity measurement is 
suitable only for detecting the presence of liquid at a given level of the tank. This level 
is represented by the length of the probe. The conductive switch is suitable for fìlling or 
emptying control with 2 to 4 relay outputs working simultaneously or for level detection 
of 2-4 independent levels (in 1 or 2 tanks) with 2 independent relay outputs.

2. Safety and responsibility

In order to provide safety in the plant, the operator is responsible for the following 
measures:
•  Products may only be used for its intended purpose, see intended use
•  Never use a damaged or defective product.  

Immediately sort out damaged product.

•  Make sure that the piping system has been installed professionally and serviced 

regularly.

•  Products and equipment shall only be installed by persons who have the required 

training, knowledge or experience.

•  Regularly train personnel in all relevant questions regarding locally applicable 

regulations, safety at work, environmental protection especially for pressurised pipes.

The personnel is responsible for the following measures:
•  Know, understand and follow the instruction manual and the advices therein.

3. Function

The level switch consists of 1 or 2 switching unit and the KLN-2 type probes. Probes are 
to be connected to the 2281 type probe socket head that can be screwed into the tank. 
lf the material of the tank or its internal insulation is not conductive then a reference 
probe should be used in addition to the one, two, three or four probe(s), if the material of 
the tank is conductive, the tank can be used as a reference probe.

4. Technical Data

4.1 Technical Data of the switching unit

Probe Voltage

5 V AC

Probe current

< 1 mA AC

Sensitivity

Adjustable: 5 kΩ ... 100 kΩ

Max. cable capacity

4 nF

Response

max. 400 ms

Setting accuracy (mech.) ± 5 %
Delay

Adjustable: 0.5 ... 10 s

Relay output

2x SPDT

Switching voltage

250 V AC1, 24 V DC

Switching current

16A AC1

Switching power

4000 vA AC1. 384 W DC

Electrical strength

4 kV

Mechanical life-span

3 x10

7

 switches

Electrical life-span

0,7x10

switches

Power supply Un

24 V AC/DC

Voltage range allowed

nominal voltage -15 %...+100 %

Power consumption

max. 2.5 VA/ W

Ambient temperature

-20°C ... +55°C

Electrical connection

max. 2.5 mm

2

 / with insulation 1.5 mm

2

Electrical protection

Class III

Ingress protection

IP 20

Mechanical connection

DIN EN 60715 rail

Mass

240 g

5. Dimensions

Switching unit: 2281-2-Relay

52

45

67,5

90

65

19

21

56,5

Separatur KLP-201

Probe KN-2xx

38

38

Ø

6

6. Installation 

•  Mount  switching unit on DIN EN 60715 rail.
•  Cut the KLN-2 type probes to the length required for level detection on site. 
•  Screw probes into the sockets.
•  Tighten the probe with an M6 nut.
•  Use separators at every 0.5 m for multiple probe devices to keep the probes apart.

7. Electrical Connection

lf the wall of the tank is conductive no reference probe is needed, ln this case terminal C 
is to be connected to the tank. On multiple probe units E1 and E2 are marked with
1,,.4, the reference probe is marked with C. Admissible length of cable between signal 
processor and probes depends on cable capacity and conductivity. Make sure E1 in 
upper level, E2 buttom level.

A1 A2

E1

E2

C

S

16 15

25

28

18

26

U

n

A1, A2 - power supply

C - reference probe

E1 - upper level probe

E2 - bottom level probe

S - shielding

15, 16, 18 - 1. relay output

25, 26, 28 - 2. relay output

E1 max. probe
E2 min. probe

C reference probe

E1

E2

8. Putting into operation

8.1 Adjustment

The green LED (

U

n

) shows that the unit is on, the energized state of the relays are 

indicated by the E1 respectively E2 LEDs. Operating mode, delay ON and delay OFF can 
be set with the DIP switch on the front panel. tE1(s) and tE2(s) potentiometers are for 
adjusting the delay time. The sensitivity setting (R potentiometer) should comply with lhe 
conductivity of the fluid. Do not set sensitivity higher than required because the vapour 
precipilation may lead to operation disturbance.

Selection of delay type for input E1

ta: delay OFF

tb: delay ON

Selection of delay type for input E2

ta: delay OFF

tb: delay ON

Inversion of function type for input E2
Function selection:

1x: monitoring two independent levels

2x: level control

Power supply indicator

`relay 1 energised´ indicator

`relay 2 energised´ indicator

Delay adjustment for E1

Delay adjustment for E2

Adjustment for probe sensitivity

1x

ON

tb

tb

Function 2x

Input inverse OFF

Delay type E2 ta

Delay type E1 ta 

E1

E2

KRK-522

tE2(s)

tE1(s)

R(kΩ)

U

n

Georg Fischer Piping Systems Ltd CH-8201 Schaffhausen

Phone +41(0)52 631 30 26 / info.ps

@

georgfischer.com / 

www.gfps.com

GFDO 6354_4 (07.14)

© Georg Fischer Rohrleitungssysteme AG

CH-8201 Schaffhausen/Schweiz, 2014

Printed in Switzerland

Instruction manual

2281 Conductive multipoint switch 
with dual channel relay

GF Piping Systems

Отзывы: