background image

Step 1: Disassemble the interlock. Place the bottom plate (holes only) Below the top right breaker and mark 

holes.  Plate is parallel to top right breaker.

Step 2: Turn off main breaker and remove panel cover. 

Step 3: Drill holes as marked on panel cover with supplied 3/16 drill bit and remove all burs from drilling cover.

Step 4: Insert screws from rear of cover, install bottom plate, and install top plate (slotted) with retaining nuts. 

Ensure proper movement. 

Model

GE-200B 

Main Breaker

200 amp Vertical throw with main on bottom

Generator Breaker

Bottom right side 2 positions

WARNING

Only qualified personnel should be working on the panel box

An amateur should 

NEVER

 open the panel box

Please follow all rules and regulations of the National Electric Code

    

Отзывы: